Energy Projects Near You

Brigstock Solar Farm (49.9 MW)

Brigstock Solar Farm is a 49.9 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 January 2022, not yet built; the record was last updated on 23 May 2023. REPD records the planning permission as expiring on 14 January 2025, but the project holds a Contracts for Difference award (AR4), so construction may have started. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtmay be out of datestatus in REPD
23 May 2023record last updated
North Northamptonshirecouncil area

REPD records the planning permission as expiring on 14 January 2025, but the project holds a Contracts for Difference award (AR4), so construction may have started.

Planning timeline

DateStage
19 February 2020Application submitted
14 January 2022Planning permission granted
14 January 2025Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
23 May 2023
Operator or applicant
Scottish Power Renewables
Planning authority
North Northamptonshire
Planning application reference
20/00207/FUL
Site area
99.0 ha
Address (REPD)
Land North Of Old Head Wood, Grafton Road, Brigstock, Kettering,
Council area (by location)
North Northamptonshire
Time to decision
99 weeks
Contracts for Difference
AR4
REPD reference
7767

Recorded together with Old Head Wood, Brigstock (battery storage, approved, not built).

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Grafton Underwoodsolar farm38approved, not built2.3
Solar Photovoltaic Panelssolar farm39.3application submitted3.1
Oakley Bush Solar Farmbattery storage10application submitted4.1
Solar PV Panelssolar farm39application submitted4.1
Barnwell Manor Wind Farmwind farm10refused on appeal4.5
Colpmans Farmsolar farm5operational7.0
New Albion Wind Farmwind farm14.4operational7.5
Bryant Field Solar Parksolar farm5permission expired8.1
Wold Cottage Solar Farmsolar farm5approved, not built8.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4419, -0.6455).