New Albion Wind Farm (14.4 MW)

New Albion Wind Farm is a 14.4 MW wind farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 18 January 2016; the record was last updated on 25 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14.4 MWwind farm
operationalstatus in REPD
25 August 2016record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
29 August 2009Application submitted
20 January 2010Planning permission granted
1 January 2015Construction started
18 January 2016Operational

Project details

Technology
wind farm
Capacity
14.4 MW
Status (REPD)
operational
Record last updated
25 August 2016
Operator or applicant
John Laing Environmental Assets Group
Planning authority
North Northamptonshire
Planning application reference
KET/2009/0549
Turbines
7
Address (REPD)
Agricultural land at Towns Close Farm, between Pipewell and Rushton and close to the A6003 Road to Corby
Council area (by location)
North Northamptonshire
Time to decision
21 weeks
REPD reference
4513

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gaultney Solar Parksolar farm20.5operational2.9
RAF Desboroughsolar farm49.9permission expired3.4
Oakley Bush Solar Farmbattery storage10application submitted3.4
Solar PV Panelssolar farm39application submitted3.4
Eckland Lodge Farm, Braybrookebattery storage500application submitted7.1
Brigstock Solar Farmsolar farm49.9approved, not built7.5
Grafton Underwoodsolar farm38approved, not built8.0
Braybrooke Battery Energy Storage Systembattery storage500application submitted8.9
Braybrooke Village North, Harborough Roadbattery storage252application submitted9.6