Energy Projects Near You

Gaultney Solar Park (20.5 MW)

Gaultney Solar Park is a 20.5 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20.5 MWsolar farm
operationalstatus in REPD
4 October 2016record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
17 June 2014Application submitted
5 September 2014Planning permission granted
1 December 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
20.5 MW
Status (REPD)
operational
Record last updated
4 October 2016
Operator or applicant
United Photovoltaics
Planning authority
North Northamptonshire
Planning application reference
KET/2014/0391
Site area
13.7 ha
Address (REPD)
Gaultney Farm, Pipewell Road, Desborough
Council area (by location)
North Northamptonshire
Time to decision
11 weeks
REPD reference
2188

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
RAF Desboroughsolar farm49.9permission expired2.2
New Albion Wind Farmwind farm14.4operational2.9
Eckland Lodge Farm, Braybrookebattery storage500application submitted4.2
Braybrooke Battery Energy Storage Systembattery storage500application submitted6.1
Solar PV Panelssolar farm39application submitted6.3
Oakley Bush Solar Farmbattery storage10application submitted6.3
Braybrooke Village North, Harborough Roadbattery storage252application submitted6.8
Draughton Maidwell Wind Farmwind farm21refused on appeal7.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4488, -0.7982).