Energy Projects Near You

Solar, wind and battery projects near Market Harborough (LE16)

17 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of LE16 (Harborough): 7 are waiting for a planning decision, 3 approved but not yet running, 3 operational. The largest live scheme is Braybrooke Battery Energy Storage System (500 MW battery storage, application submitted on 16 July 2025, no decision recorded), 2.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects within 10 km
7awaiting a decision
3approved, not running
3operational

Projects within 10 km of LE16

Projects of 1 MW and more (12)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Braybrooke Village North, Harborough Roadbattery storagebattery storage252application submittedupdated Sep 2025Jul 2025—Sep 2025North Northamptonshire2.2
Braybrooke Battery Energy Storage Systembattery storagebattery storage500application submittedupdated Oct 2025Jul 2025—Oct 2025North Northamptonshire2.9
Airfield Farm (Leicestershire)wind farmwind farm7.5refusedupdated Jul 2014Sep 2009refused Jan 2010Jul 2014Harborough3.2
Land at Meadow Farmsolar farmsolar farm5operationalupdated May 2017Jul 2015granted Oct 2015May 2017Harborough3.8
Eckland Lodge Farm, Braybrookebattery storagebattery storage500application submittedupdated Sep 2025Aug 2025—Sep 2025North Northamptonshire4.3
Eckland Lodge Farmsolar farmsolar farm2.9operationalupdated Jun 2017Oct 2014granted Jul 2015Jun 2017North Northamptonshire4.8
VPK Desborough, Stoke Albany Road, Desborough Solar PV Arraysrooftop solarrooftop solar1.9approved, not builtupdated Nov 2025Jul 2025granted Sep 2025Nov 2025North Northamptonshire6.1
West Lodge Farm Solar Arraysolar farmsolar farm1.2application submittedupdated Mar 2026Dec 2025—Mar 2026North Northamptonshire6.9
RAF Desboroughsolar farmsolar farm49.9permission expiredupdated Feb 2020Apr 2015granted Aug 2015Feb 2020North Northamptonshire7.2
Gaultney Solar Parksolar farmsolar farm20.5operationalupdated Oct 2016Jun 2014granted Sep 2014Oct 2016North Northamptonshire7.9
Sunnydale Farmbattery storagebattery storage4.2abandonedupdated Jul 2020Sep 2017—Jul 2020Harborough9.5
Theddingworth solar farmsolar farmsolar farm30application withdrawnupdated Aug 2015Jun 2014—Aug 2015Harborough9.6
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Robert Smyth School, Burnmill Roadrooftop solarrooftop solar0.2approved, not builtupdated Aug 2024Mar 2024granted Jul 2024Aug 2024Harborough1.6
Astley Grange Farm, Back Lanerooftop solarrooftop solar0.3approved, not builtupdated Jul 2025May 2025granted Jul 2025Jul 2025Harborough4.8
West Lodge Farm, Pipewell Roadsolar farmsolar farm0.9application submittedupdated Mar 2026Dec 2025—Mar 2026North Northamptonshire6.9
West Lodge Rural Centre, Back Lanerooftop solarrooftop solar0.2application submittedupdated Nov 2024Oct 2024—Nov 2024North Northamptonshire6.9
West Lodge Farm Solar Arraybattery storagebattery storage—application submittedupdated Mar 2026Dec 2025—Mar 2026North Northamptonshire6.9

Distance from the average position of the LE16 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm720302.1
Rooftop solar413002.5
Wind farm100010
Battery storage540001,252

MW in pipeline: pending, approved and under-construction capacity.

How Harborough decides solar, wind and battery applications

ApplicationsHarboroughUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 545%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

All projects in Harborough

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.