Energy Projects Near You

Land at Meadow Farm (5 MW solar farm)

Land at Meadow Farm is a 5 MW solar farm project in Harborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 10 March 2017; the record was last updated on 26 May 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
26 May 2017record last updated
Harboroughcouncil area

Planning timeline

DateStage
22 July 2015Application submitted
8 October 2015Planning permission granted
9 January 2017Construction started
10 March 2017Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
26 May 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Harborough
Planning application reference
15/01116/FUL
Site area
14.5 ha
Address (REPD)
Land at Meadow Farm, Main Street, Thorpe Langton, Market Harborough, Leicestershire
Council area (by location)
Harborough
Time to decision
11 weeks
REPD reference
5385

Who decides

ApplicationsHarboroughUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 545%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Airfield Farm (Leicestershire)wind farm7.5refused2.6
Braybrooke Village North, Harborough Roadbattery storage252application submitted5.9
Braybrooke Battery Energy Storage Systembattery storage500application submitted6.6
Eckland Lodge Farm, Braybrookebattery storage500application submitted8.0
Theddingworth solar farmsolar farm30application withdrawn9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.5173, -0.9199).