RAF Desborough (49.9 MW solar farm)

RAF Desborough is a 49.9 MW solar farm project in North Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 26 August 2018; the record was last updated on 4 February 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
permission expiredstatus in REPD
4 February 2020record last updated
North Northamptonshirecouncil area

Planning timeline

DateStage
9 April 2015Application submitted
26 August 2015Planning permission granted
26 August 2018Permission expired

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
permission expired
Record last updated
4 February 2020
Operator or applicant
RAF Desb
Planning authority
North Northamptonshire
Planning application reference
KET/2015/0297
Site area
112.8 ha
Address (REPD)
Desborough Airfield, Desborough Road, Stoke Albany, Market Harborough, Leicestershire
Council area (by location)
North Northamptonshire
Time to decision
20 weeks
REPD reference
4968

Who decides

ApplicationsNorth NorthamptonshireUK
Decided applications (solar, wind, battery)6810,236
Refused11 (16%)19%
Solar refused2 of 4412%
Onshore wind refused5 of 1145%
Battery storage refused4 of 1316%
Median time from submission to decision11.4 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gaultney Solar Parksolar farm20.5operational2.2
New Albion Wind Farmwind farm14.4operational3.4
Eckland Lodge Farm, Braybrookebattery storage500application submitted4.6
Braybrooke Battery Energy Storage Systembattery storage500application submitted6.2
Solar PV Panelssolar farm39application submitted6.6
Oakley Bush Solar Farmbattery storage10application submitted6.6
Braybrooke Village North, Harborough Roadbattery storage252application submitted6.7
Draughton Maidwell Wind Farmwind farm21refused on appeal9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4687, -0.7955).