Energy Projects Near You

Brixworth Landfill, Scaldwell Road Solar Array & Battery Storage (5.6 MW)

Brixworth Landfill, Scaldwell Road Solar Array & Battery Storage is a 5.6 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 2 October 2025, no decision recorded; the record was last updated on 6 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.6 MWsolar farm
application submittedstatus in REPD
6 November 2025record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
2 October 2025Application submitted

Project details

Technology
solar farm
Capacity
5.6 MW
Status (REPD)
application submitted
Record last updated
6 November 2025
Operator or applicant
SUEZ Recycling and Recovery UK Limited
Planning authority
West Northamptonshire
Planning application reference
2025/4312/MAF
Site area
8.0 ha
Address (REPD)
Brixworth Landfill Site Scaldwell Road Brixworth
Council area (by location)
West Northamptonshire
Name in REPD
Brixworth Landfill, Scaldwell Road - Solar Array & Battery Storage
REPD reference
19118

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brixworth Windfarmwind farm13application withdrawn2.5
Hall Farm (Hannington)solar farm10.9permission expired5.0
Welford Road Solar Farmsolar farm5application submitted5.9
Draughton Maidwell Wind Farmwind farm21refused on appeal7.3
Sywell Roadsolar farm5operational8.3
Kelmarsh Wind Farm (Resubmission)wind farm12.5operational9.2
Green Hill Solar Farm & Battery Storagesolar farm600application submitted9.5
Stonebrig Lanesolar farm18.8refused9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3316, -0.8901).