Energy Projects Near You

Brixworth Windfarm (13 MW)

Brixworth Windfarm is a 13 MW wind farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application withdrawn on 11 March 2009; the record was last updated on 22 June 2011.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13 MWwind farm
application withdrawnstatus in REPD
22 June 2011record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
29 August 2008Application submitted
11 March 2009Application withdrawn

Project details

Technology
wind farm
Capacity
13 MW
Status (REPD)
application withdrawn
Record last updated
22 June 2011
Operator or applicant
Bolsterstone Plc
Planning authority
West Northamptonshire
Planning application reference
DA/2008/1252
Turbines
6
Address (REPD)
Land adjacent to Harborough Road, between Brixworth and Hanging Houghton
Council area (by location)
West Northamptonshire
REPD reference
3066

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Brixworth Landfill, Scaldwell Road Solar Array & Battery Storagesolar farm5.6application submitted2.5
Draughton Maidwell Wind Farmwind farm21refused on appeal5.7
Hall Farm (Hannington)solar farm10.9permission expired6.4
Kelmarsh Wind Farm (Resubmission)wind farm12.5operational6.7
Welford Road Solar Farmsolar farm5application submitted7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3505, -0.9099).