Solar, wind and battery projects near Northampton (NN5)
35 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NN5 (West Northamptonshire): 9 are waiting for a planning decision, 14 approved but not yet running, 5 operational. The largest live scheme is Glassthorpe Hill, Flore Solar Farm (49.9 MW solar farm, application submitted on 20 April 2022, no decision recorded; REPD status may be out of date), 7.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NN5
Projects of 1 MW and more (16)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Cinch Stadium, Franklin’s Gardens Solarrooftop solar | rooftop solar | 8.8 | operationalupdated May 2022 | — | — | May 2022 | West Northamptonshire | 1.4 |
| Nectar Way Regional Distribution Centrerooftop solar | rooftop solar | 1 | operationalupdated Sep 2015 | — | — | Sep 2015 | West Northamptonshire | 3.4 |
| Sainsburys, Style Wayrooftop solar | rooftop solar | 4.5 | application submitted | Jun 2026 | — | — | West Northamptonshire | 3.6 |
| Land off the A5199, Brampton Valley Waysolar farm | solar farm | 4.2 | refusedupdated Mar 2015 | Nov 2014 | refused Mar 2015 | Mar 2015 | West Northamptonshire | 3.8 |
| Welford Road Solar Farmsolar farm | solar farm | 5 | application submittedupdated Jan 2025 | Jan 2025 | — | Jan 2025 | West Northamptonshire | 4.1 |
| Kislingbury Road Solar Farmsolar farm | solar farm | 5 | refusedupdated Jul 2015 | May 2015 | refused Jul 2015 | Jul 2015 | West Northamptonshire | 4.7 |
| Land to the south of Hill Farmsolar farm | solar farm | 6.8 | operationalupdated Apr 2017 | Oct 2015 | granted Jan 2016 | Apr 2017 | West Northamptonshire | 5.3 |
| Milton Road, Gayton Solar Farmsolar farm | solar farm | 46.4 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | West Northamptonshire | 6.0 |
| Asda Brackmills Distribution Depotwind turbine | wind turbine | 2 | refusedupdated Dec 2014 | Dec 2007 | refused Nov 2008 | Dec 2014 | West Northamptonshire | 6.6 |
| Glassthorpe Hill, Flore Solar Farmsolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Feb 2026 | Apr 2022 | — | Feb 2026 | West Northamptonshire | 7.5 |
| Preston, Deanery Solar Farmsolar farm | solar farm | 27.8 | application submitted may be out of dateupdated Jan 2024 | Oct 2023 | — | Jan 2024 | West Northamptonshire | 8.1 |
| Preston Lodgesolar farm | solar farm | 4.5 | refusedupdated Sep 2016 | Mar 2016 | refused Jun 2016 | Sep 2016 | West Northamptonshire | 8.5 |
| Land South of Knock Lanesolar farm | solar farm | 4 | abandonedupdated Dec 2016 | Oct 2015 | granted Dec 2015 | Dec 2016 | West Northamptonshire | 9.0 |
| East Haddonsolar farm | solar farm | 2 | under constructionupdated Apr 2024 | May 2022 | granted Sep 2022 | Apr 2024 | West Northamptonshire | 9.1 |
| Land South of Knock Lanesolar farm | solar farm | 4 | operationalupdated Dec 2016 | Jun 2015 | granted Apr 2016 | Dec 2016 | West Northamptonshire | 9.3 |
| Brixworth Landfill, Scaldwell Road Solar Array & Battery Storagesolar farm | solar farm | 5.6 | application submittedupdated Nov 2025 | Oct 2025 | — | Nov 2025 | West Northamptonshire | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (19)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Sainsburys, Gambrel Roadrooftop solar | rooftop solar | 0.7 | application submitted | May 2026 | — | — | West Northamptonshire | 0.8 |
| Io Centre, Unit 5, 6, 7 & 8, Barn Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Dec 2024 | granted Feb 2025 | Mar 2025 | West Northamptonshire | 1.4 |
| Ladys Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Sep 2025 | Dec 2025 | West Northamptonshire | 3.0 |
| Clannell Road Tesco (Northampton South)rooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2023 | Jan 2020 | granted Mar 2020 | May 2023 | West Northamptonshire | 3.9 |
| Wootton Hall Park, Mereway - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2026 | Oct 2025 | granted May 2026 | Jul 2026 | West Northamptonshire | 4.5 |
| Penvale Road - Micro Energy Battery Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Dec 2025 | Aug 2025 | — | Dec 2025 | West Northamptonshire | 4.8 |
| Wieland Nemco, Pennard Closerooftop solar | rooftop solar | 0.1 | operationalupdated Aug 2023 | Jan 2023 | granted Feb 2023 | Aug 2023 | West Northamptonshire | 5.7 |
| Upper Heyford Roundabout, Daventry Link Roadbattery storage | battery storage | 0.2 | application submittedupdated Dec 2025 | Oct 2025 | — | Dec 2025 | West Northamptonshire | 5.9 |
| Campion School, Kislingbury Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | West Northamptonshire | 6.0 |
| Salthouse Road - Roof Mounted Solar Photovoltaicsrooftop solar | rooftop solar | 0.2 | refusedupdated Sep 2024 | May 2024 | refused Aug 2024 | Sep 2024 | West Northamptonshire | 6.1 |
| Wickes Northampton Distribution Centre, Salthouse Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Oct 2025 | Dec 2025 | West Northamptonshire | 6.1 |
| Moulton Park Industrial Estate - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Oct 2025 | Dec 2025 | West Northamptonshire | 6.2 |
| Octagon Way, Weston Favell Retail Parkbattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Sep 2025 | Dec 2025 | West Northamptonshire | 6.9 |
| Riverside Prime Car Showroom, Carousel Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | West Northamptonshire | 7.1 |
| Riverside Prime, Carousel Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Mar 2023 | granted May 2023 | Sep 2023 | West Northamptonshire | 7.1 |
| Northampton Gateway Srfirooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2025 | Jul 2025 | granted Sep 2025 | Dec 2025 | West Northamptonshire | 7.3 |
| Edgemead Closerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Mar 2023 | granted Apr 2023 | Jun 2023 | West Northamptonshire | 7.6 |
| Cheaney Drive, Grange Park Industrial Estate Solar PV Modulesrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2024 | Dec 2023 | granted Feb 2024 | Mar 2024 | West Northamptonshire | 7.7 |
| Brixworth Landfill, Scaldwell Road Solar Array & Battery Storagebattery storage | battery storage | — | application submittedupdated Nov 2025 | Oct 2025 | — | Nov 2025 | West Northamptonshire | 10.0 |
Distance from the average position of the NN5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 5 | 1 | 2 | 3 | 137 |
| Rooftop solar | 16 | 2 | 10 | 3 | 1 | 9.2 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 6 | 2 | 3 | 0 | 0 | 0.8 |
MW in pipeline: pending, approved and under-construction capacity.
How West Northamptonshire decides solar, wind and battery applications
| Applications | West Northamptonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 87 | 10,236 |
| Refused | 23 (26%) | 19% |
| Solar refused | 12 of 65 | 12% |
| Onshore wind refused | 9 of 12 | 45% |
| Battery storage refused | 2 of 10 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 10 | — |
All projects in West Northamptonshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NN5, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.