Solar, wind and battery projects near Northampton (NN4)
40 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NN4 (West Northamptonshire): 6 are waiting for a planning decision, 15 approved but not yet running, 11 operational. The largest live scheme is Milton Road, Gayton Solar Farm (46.4 MW solar farm, application submitted on 11 July 2025, no decision recorded), 3.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of NN4
Projects of 1 MW and more (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Asda Brackmills Distribution Depotwind turbine | wind turbine | 2 | refusedupdated Dec 2014 | Dec 2007 | refused Nov 2008 | Dec 2014 | West Northamptonshire | 2.8 |
| Cinch Stadium, Franklin’s Gardens Solarrooftop solar | rooftop solar | 8.8 | operationalupdated May 2022 | — | — | May 2022 | West Northamptonshire | 3.3 |
| Milton Road, Gayton Solar Farmsolar farm | solar farm | 46.4 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | West Northamptonshire | 3.9 |
| Kislingbury Road Solar Farmsolar farm | solar farm | 5 | refusedupdated Jul 2015 | May 2015 | refused Jul 2015 | Jul 2015 | West Northamptonshire | 4.1 |
| Preston, Deanery Solar Farmsolar farm | solar farm | 27.8 | application submitted may be out of dateupdated Jan 2024 | Oct 2023 | — | Jan 2024 | West Northamptonshire | 4.1 |
| Nectar Way Regional Distribution Centrerooftop solar | rooftop solar | 1 | operationalupdated Sep 2015 | — | — | Sep 2015 | West Northamptonshire | 4.3 |
| Preston Lodgesolar farm | solar farm | 4.5 | refusedupdated Sep 2016 | Mar 2016 | refused Jun 2016 | Sep 2016 | West Northamptonshire | 4.5 |
| Sainsburys, Style Wayrooftop solar | rooftop solar | 4.5 | application submitted | Jun 2026 | — | — | West Northamptonshire | 4.5 |
| Land to the south of Hill Farmsolar farm | solar farm | 6.8 | operationalupdated Apr 2017 | Oct 2015 | granted Jan 2016 | Apr 2017 | West Northamptonshire | 5.4 |
| Land South of Knock Lanesolar farm | solar farm | 4 | abandonedupdated Dec 2016 | Oct 2015 | granted Dec 2015 | Dec 2016 | West Northamptonshire | 5.8 |
| Land South of Knock Lanesolar farm | solar farm | 4 | operationalupdated Dec 2016 | Jun 2015 | granted Apr 2016 | Dec 2016 | West Northamptonshire | 5.8 |
| M1 Wind Farmwind farm | wind farm | 7.2 | operationalupdated Aug 2014 | Nov 2011 | granted May 2013 | Aug 2014 | West Northamptonshire | 6.3 |
| Land East of Horton Roadsolar farm | solar farm | 4.9 | operationalupdated Jul 2018 | Oct 2014 | granted May 2015 | Jul 2018 | West Northamptonshire | 7.2 |
| Land off the A5199, Brampton Valley Waysolar farm | solar farm | 4.2 | refusedupdated Mar 2015 | Nov 2014 | refused Mar 2015 | Mar 2015 | West Northamptonshire | 7.5 |
| Welford Road Solar Farmsolar farm | solar farm | 5 | application submittedupdated Jan 2025 | Jan 2025 | — | Jan 2025 | West Northamptonshire | 7.7 |
| Bulls Head Farm Northsolar farm | solar farm | 4.7 | operationalupdated Feb 2015 | Dec 2013 | granted Apr 2014 | Feb 2015 | West Northamptonshire | 9.0 |
| Manor Farm (Horton)solar farm | solar farm | 5 | operationalupdated May 2016 | Jul 2014 | granted Nov 2014 | May 2016 | West Northamptonshire | 9.2 |
| Salcey Green Farmsolar farm | solar farm | 5 | refusedupdated Jul 2024 | Apr 2024 | refused Jul 2024 | Jul 2024 | Milton Keynes | 9.5 |
| Stonepit Farmsolar farm | solar farm | 5 | operationalupdated May 2016 | Sep 2013 | granted Dec 2013 | May 2016 | West Northamptonshire | 9.6 |
| Salcey Solar Farmbattery storage | battery storage | 1 | operationalupdated Mar 2019 | Mar 2016 | — | Mar 2019 | Milton Keynes | 9.6 |
Smaller schemes under 1 MW, mostly rooftop solar (20)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Wootton Hall Park, Mereway - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jul 2026 | Oct 2025 | granted May 2026 | Jul 2026 | West Northamptonshire | 0.1 |
| Clannell Road Tesco (Northampton South)rooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2023 | Jan 2020 | granted Mar 2020 | May 2023 | West Northamptonshire | 0.8 |
| Penvale Road - Micro Energy Battery Storagebattery storage | battery storage | 0.2 | application withdrawnupdated Dec 2025 | Aug 2025 | — | Dec 2025 | West Northamptonshire | 0.9 |
| Wieland Nemco, Pennard Closerooftop solar | rooftop solar | 0.1 | operationalupdated Aug 2023 | Jan 2023 | granted Feb 2023 | Aug 2023 | West Northamptonshire | 2.4 |
| Salthouse Road - Roof Mounted Solar Photovoltaicsrooftop solar | rooftop solar | 0.2 | refusedupdated Sep 2024 | May 2024 | refused Aug 2024 | Sep 2024 | West Northamptonshire | 2.9 |
| Wickes Northampton Distribution Centre, Salthouse Roadrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Oct 2025 | Dec 2025 | West Northamptonshire | 2.9 |
| Ladys Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Sep 2025 | Dec 2025 | West Northamptonshire | 3.0 |
| Cheaney Drive, Grange Park Industrial Estate Solar PV Modulesrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2024 | Dec 2023 | granted Feb 2024 | Mar 2024 | West Northamptonshire | 3.4 |
| Northampton Gateway Srfirooftop solar | rooftop solar | 0.6 | approved, not builtupdated Dec 2025 | Jul 2025 | granted Sep 2025 | Dec 2025 | West Northamptonshire | 3.4 |
| Sainsburys, Gambrel Roadrooftop solar | rooftop solar | 0.7 | application submitted | May 2026 | — | — | West Northamptonshire | 3.7 |
| Riverside Prime Car Showroom, Carousel Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2023 | Mar 2023 | granted May 2023 | Jun 2023 | West Northamptonshire | 5.6 |
| Riverside Prime, Carousel Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Sep 2023 | Mar 2023 | granted May 2023 | Sep 2023 | West Northamptonshire | 5.7 |
| Io Centre, Unit 5, 6, 7 & 8, Barn Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Dec 2024 | granted Feb 2025 | Mar 2025 | West Northamptonshire | 5.8 |
| Octagon Way, Weston Favell Retail Parkbattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Sep 2025 | Dec 2025 | West Northamptonshire | 6.3 |
| Horton Lodge Farmsolar farm | solar farm | 0.1 | approved, not built may be out of dateupdated Nov 2022 | Jul 2022 | granted Oct 2022 | Nov 2022 | West Northamptonshire | 6.8 |
| Campion School, Kislingbury Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | West Northamptonshire | 7.3 |
| Moulton Park Industrial Estate - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Oct 2025 | Dec 2025 | West Northamptonshire | 7.3 |
| Station Farmsolar farm | solar farm | 0.1 | approved, not built may be out of dateupdated May 2022 | Apr 2022 | granted Jun 2022 | May 2022 | West Northamptonshire | 7.9 |
| Edgemead Closerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Mar 2023 | granted Apr 2023 | Jun 2023 | West Northamptonshire | 8.4 |
| Upper Heyford Roundabout, Daventry Link Roadbattery storage | battery storage | 0.2 | application submittedupdated Dec 2025 | Oct 2025 | — | Dec 2025 | West Northamptonshire | 8.4 |
Distance from the average position of the NN4 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 16 | 3 | 2 | 6 | 4 | 79.5 |
| Rooftop solar | 16 | 2 | 10 | 3 | 1 | 9.2 |
| Wind farm | 1 | 0 | 0 | 1 | 0 | 0 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 6 | 1 | 3 | 1 | 0 | 0.8 |
MW in pipeline: pending, approved and under-construction capacity.
How West Northamptonshire decides solar, wind and battery applications
| Applications | West Northamptonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 87 | 10,236 |
| Refused | 23 (26%) | 19% |
| Solar refused | 12 of 65 | 12% |
| Onshore wind refused | 9 of 12 | 45% |
| Battery storage refused | 2 of 10 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 10 | — |
All projects in West Northamptonshire
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NN4, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.