Energy Projects Near You

Land to the south of Hill Farm (6.8 MW solar farm)

Land to the south of Hill Farm is a 6.8 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2017; the record was last updated on 20 April 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6.8 MWsolar farm
operationalstatus in REPD
20 April 2017record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
22 October 2015Application submitted
14 January 2016Planning permission granted
12 December 2016Construction started
31 March 2017Operational

Project details

Technology
solar farm
Capacity
6.8 MW
Status (REPD)
operational
Record last updated
20 April 2017
Operator or applicant
TGC Renewables
Planning authority
West Northamptonshire
Planning application reference
S/2015/2469/MAF
Site area
16.4 ha
Address (REPD)
Land to the south of Hill Farm, Gayton Road, Kislingbury
Council area (by location)
West Northamptonshire
Time to decision
12 weeks
REPD reference
5880

Earlier applications for this site

ApplicationMWSubmittedOutcome
Land to the south of Hill Farm S/2015/1190/MAF6.827 May 2015withdrawn 16 July 2015

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kislingbury Road Solar Farmsolar farm5refused1.3
Milton Road, Gayton Solar Farmsolar farm46.4application submitted2.6
Cinch Stadium, Franklin’s Gardens Solarrooftop solar8.8operational5.5
Glassthorpe Hill, Flore Solar Farmsolar farm49.9application submitted6.6
Preston, Deanery Solar Farmsolar farm27.8application submitted9.2
Welford Road Solar Farmsolar farm5application submitted9.3
M1 Wind Farmwind farm7.2operational9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2061, -0.9772).