Energy Projects Near You

Glassthorpe Hill, Flore Solar Farm (49.9 MW)

Glassthorpe Hill, Flore Solar Farm is a 49.9 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 20 April 2022, no decision recorded; the record was last updated on 17 February 2026. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
17 February 2026record last updated
West Northamptonshirecouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
20 April 2022Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
17 February 2026
Operator or applicant
EDF Renewables
Planning authority
West Northamptonshire
Planning application reference
WND/2022/0410
Site area
96.9 ha
Address (REPD)
Glassthorpe Hill & Land Off Brington Road, Flore,
Council area (by location)
West Northamptonshire
Contracts for Difference
AR7a
Name in REPD
Glassthorpe Hill, Flore - Solar Farm
REPD reference
11380

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Newnham Grange Farmbattery storage15application submitted5.2
Land to the south of Hill Farmsolar farm6.8operational6.6
Kislingbury Road Solar Farmsolar farm5refused7.6
Crockwell Hill Solar Farmsolar farm6approved, not built7.9
Crockwell Hill Solar Farmsolar farm6application submitted7.9
Watford Gap Wind Farmwind farm10refused7.9
Cinch Stadium, Franklin’s Gardens Solarrooftop solar8.8operational8.7
Milton Road, Gayton Solar Farmsolar farm46.4application submitted9.2
Welford Road Solar Farmsolar farm5application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2476, -1.0469).