Crockwell Hill Solar Farm (6 MW, REPD 17286)
Crockwell Hill Solar Farm is a 6 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 16 September 2024, no decision recorded; the record was last updated on 5 November 2024.
6 MWsolar farm
application submittedstatus in REPD
5 November 2024record last updated
West Northamptonshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 16 September 2024 | Application submitted |
Project details
- Technology
- solar farm
- Capacity
- 6 MW
- Status (REPD)
- application submitted
- Record last updated
- 5 November 2024
- Operator or applicant
- PS Renewables Limited
- Planning authority
- West Northamptonshire
- Planning application reference
- 2024/4395/MAF
- Site area
- 7.7 ha
- Address (REPD)
- E/O Crockwell Hill, Watford Village, Daventry
- Council area (by location)
- West Northamptonshire
- Name in REPD
- Crockwell Hill - Solar Farm
- REPD reference
- 17286
Who decides
| Applications | West Northamptonshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 87 | 10,236 |
| Refused | 23 (26%) | 19% |
| Solar refused | 12 of 65 | 12% |
| Onshore wind refused | 9 of 12 | 45% |
| Battery storage refused | 2 of 10 | 16% |
| Median time from submission to decision | 13.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 7 / 10 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Crockwell Hill Solar Farm | solar farm | 6 | approved, not built | <0.1 |
| Watford Gap Wind Farm | wind farm | 10 | refused | 1.6 |
| The A361, Ashby St Ledgers Solar Farm | solar farm | 35 | application submitted | 3.9 |
| Crick Solar Farm | solar farm | 49.9 | approved, not built | 4.0 |
| Watford Lodge | wind farm | 12.5 | operational | 4.0 |
| Newnham Grange Farm | battery storage | 15 | application submitted | 4.6 |
| Crick Road | solar farm | 49.9 | under construction | 7.3 |
| Rugby Road, Kilsby - Rainsbrook Solar Farm | solar farm | 13 | approved, not built | 7.3 |
| Glassthorpe Hill, Flore Solar Farm | solar farm | 49.9 | application submitted | 7.9 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.2943, -1.1342).