Energy Projects Near You

Watford Lodge (12.5 MW wind farm)

Watford Lodge is a 12.5 MW wind farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 23 November 2015; the record was last updated on 17 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.5 MWwind farm
operationalstatus in REPD
17 December 2015record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
19 August 2008Application submitted
20 April 2011Refused by the planning authority
21 December 2011Planning permission granted
21 December 2011Appeal allowed
1 December 2014Construction started
23 November 2015Operational

Project details

Technology
wind farm
Capacity
12.5 MW
Status (REPD)
operational
Record last updated
17 December 2015
Operator or applicant
Broadview Energy
Planning authority
West Northamptonshire
Planning application reference
DA/2009/0620
Turbines
5
Address (REPD)
runs from Watford to West Hadon Road along norhtern side of railway
Council area (by location)
West Northamptonshire
Time to decision
174 weeks
REPD reference
4424

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Watford Gap Wind Farmwind farm10refused2.6
Crick Solar Farmsolar farm49.9approved, not built3.1
Crockwell Hill Solar Farmsolar farm6application submitted4.0
Crockwell Hill Solar Farmsolar farm6approved, not built4.0
Crick Roadsolar farm49.9under construction4.2
Winwickwind farm12.3operational5.3
Yelvertoft Wind Farmwind farm16operational6.1
The A361, Ashby St Ledgers Solar Farmsolar farm35application submitted6.2
Rugby Road, Kilsby - Rainsbrook Solar Farmsolar farm13approved, not built6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3265, -1.1069).