The A361, Ashby St Ledgers Solar Farm (35 MW)

The A361, Ashby St Ledgers Solar Farm is a 35 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 22 August 2025, no decision recorded; the record was last updated on 28 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

35 MWsolar farm
application submittedstatus in REPD
28 October 2025record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
22 August 2025Application submitted

Project details

Technology
solar farm
Capacity
35 MW
Status (REPD)
application submitted
Record last updated
28 October 2025
Operator or applicant
Elgin Energy Esco Limited
Planning authority
West Northamptonshire
Planning application reference
2025/3243/MAF
Site area
71.7 ha
Address (REPD)
The A361, Ashby St Ledgers, Daventry
Council area (by location)
West Northamptonshire
Name in REPD
The A361, Ashby St Ledgers - Solar Farm
REPD reference
19652

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crick Solar Farmsolar farm49.9approved, not built3.7
Crockwell Hill Solar Farmsolar farm6application submitted3.9
Crockwell Hill Solar Farmsolar farm6approved, not built3.9
Rugby Road, Kilsby - Rainsbrook Solar Farmsolar farm13approved, not built4.9
Watford Gap Wind Farmwind farm10refused4.9
Watford Lodgewind farm12.5operational6.2
Newnham Grange Farmbattery storage15application submitted7.2
Crick Roadsolar farm49.9under construction7.2
Yelvertoft Wind Farmwind farm16operational8.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3036, -1.1894).