Crick Road (49.9 MW solar farm)

Crick Road is a 49.9 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 3 October 2022; the record was last updated on 25 May 2023.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
under constructionstatus in REPD
25 May 2023record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
8 April 2020Application submitted
19 November 2020Planning permission granted
3 October 2022Construction started

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
under construction
Record last updated
25 May 2023
Operator or applicant
Lightrock Power / Bluefield Solar Income Fund
Planning authority
West Northamptonshire
Planning application reference
DA/2020/0200
Site area
80.9 ha
Address (REPD)
Land at, Crick Road, Yelvertoft, Northampton, Northamptonshire
Council area (by location)
West Northamptonshire
Time to decision
32 weeks
Contracts for Difference
AR4
REPD reference
7954

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Yelvertoft Wind Farmwind farm16operational2.0
Crick Solar Farmsolar farm49.9approved, not built3.6
Watford Lodgewind farm12.5operational4.2
Lilbourne Wind Farmwind farm10operational4.4
Rugby Road, Kilsby - Rainsbrook Solar Farmsolar farm13approved, not built4.6
Winwickwind farm12.3operational5.0
Swinford Wind Farmsolar farm20under construction6.1
Swinford Wind Farmwind farm22operational6.2
Watford Gap Wind Farmwind farm10refused6.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3596, -1.1357).