Swinford Wind Farm (20 MW)

Swinford Wind Farm is a 20 MW solar farm project in Harborough, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction; the record was last updated on 23 May 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
under constructionstatus in REPD
23 May 2022record last updated
Harboroughcouncil area

Planning timeline

DateStage
16 December 2019Application submitted
22 December 2021Planning permission granted

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
under construction
Record last updated
23 May 2022
Operator or applicant
Vattenfall
Planning authority
Harborough
Planning application reference
19/01853/FUL
Site area
25.5 ha
Address (REPD)
Land At Swinford Corner, Lutterworth Road, Swinford, Lutterworth, Leicestershire
Council area (by location)
Harborough
Time to decision
105 weeks
REPD reference
6720

Who decides

ApplicationsHarboroughUK
Decided applications (solar, wind, battery)2010,236
Refused5 (25%)19%
Solar refused1 of 1412%
Onshore wind refused4 of 545%
Battery storage refused0 of 116%
Median time from submission to decision13.1 weeks17.0 weeks
Appeals lodged / allowed0 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Swinford Wind Farmwind farm22operational0.1
Lilbourne Wind Farmwind farm10operational1.9
Energy Park Facility & Battery Storagebattery storage1,000application submitted2.7
Northfield House Solar Farmsolar farm26operational4.1
Yelvertoft Wind Farmwind farm16operational4.2
School Farmsolar farm12refused4.9
Solar Farm & Battery Storage at North of South Kilworth Roadsolar farm49.9approved, not built5.0
Swift Wind Farmwind farm8application withdrawn5.5
Crick Roadsolar farm49.9under construction6.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4113, -1.1659).