School Farm (12 MW solar farm)

School Farm is a 12 MW solar farm project in Rugby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 28 September 2016; the record was last updated on 4 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
refusedstatus in REPD
4 October 2016record last updated
Rugbycouncil area

Planning timeline

DateStage
4 November 2014Application submitted
28 September 2016Refused by the planning authority

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
refused
Record last updated
4 October 2016
Operator or applicant
Hive Energy
Planning authority
Rugby
Planning application reference
R13/1401
Site area
24.3 ha
Address (REPD)
Fields South Of Black Spinney, Kilsby, Churchover, Rugby
Council area (by location)
Rugby
Time to decision
99 weeks
REPD reference
4793

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Swift Wind Farmwind farm8application withdrawn1.1
Swift Wind Farm (Bransford Bridge)wind farm8refused on appeal1.5
Northfield House Solar Farmsolar farm26operational1.7
Harborough Fields Farmsolar farm27permission expired2.1
Streetfield Farmsolar farm18.3operational2.2
Bransford Bridgewind farm18refused2.2
Swinford Wind Farmwind farm22operational4.9
Swinford Wind Farmsolar farm20under construction4.9
Energy Park Facility & Battery Storagebattery storage1,000application submitted5.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4251, -1.2347).