Harborough Fields Farm (27 MW solar farm)

Harborough Fields Farm is a 27 MW solar farm project in Rugby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 29 March 2024; the record was last updated on 12 July 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

27 MWsolar farm
permission expiredstatus in REPD
12 July 2022record last updated
Rugbycouncil area

Planning timeline

DateStage
4 June 2020Application submitted
29 March 2021Planning permission granted
29 March 2024Permission expired

Project details

Technology
solar farm
Capacity
27 MW
Status (REPD)
permission expired
Record last updated
12 July 2022
Operator or applicant
Warwickshire Solar 1
Planning authority
Rugby
Planning application reference
R20/0438
Site area
43.3 ha
Address (REPD)
Harborough Fields Farm, Churchover Lane, Churchover, Rugby, Warwickshire
Council area (by location)
Rugby
Time to decision
43 weeks
REPD reference
7896

The scheme also includes battery storage, recorded separately in REPD (permission expired).

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bransford Bridgewind farm18refused0.3
Swift Wind Farm (Bransford Bridge)wind farm8refused on appeal1.1
School Farmsolar farm12refused2.1
Streetfield Farmsolar farm18.3operational2.2
Swift Wind Farmwind farm8application withdrawn2.3
Northfield House Solar Farmsolar farm26operational3.7
Bungalow Farm, Smeaton Lanebattery storage60application submitted6.5
Bungalow Farm, Smeaton Lanebattery storage60application submitted6.6
Coal Pit Lane, Willey Solar Farmsolar farm16application submitted6.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4215, -1.2651).