Bungalow Farm, Smeaton Lane (60 MW battery storage, REPD 16585)

Bungalow Farm, Smeaton Lane is a 60 MW battery storage project in Rugby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 28 January 2025, no decision recorded; the record was last updated on 14 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

60 MWbattery storage
application submittedstatus in REPD
14 February 2025record last updated
Rugbycouncil area

Planning timeline

DateStage
28 January 2025Application submitted

Project details

Technology
battery storage (stand-alone storage)
Capacity
60 MW
Status (REPD)
application submitted
Record last updated
14 February 2025
Operator or applicant
Integrum Renewable Energy Limited
Planning authority
Rugby
Planning application reference
R24/1166
Address (REPD)
Bungalow Farm, Smeaton Lane, Stretton Under Fosse, Rugby
Council area (by location)
Rugby
Name in REPD
Bungalow Farm, Smeaton Lane - Battery Energy Storage
REPD reference
16585

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bungalow Farm, Smeaton Lanebattery storage60application submitted<0.1
T Main Road, Anstybattery storage200approved, not built4.4
Coal Pit Lane, Willey Solar Farmsolar farm16application submitted6.2
Lentons Lane Solar Farmsolar farm30refused6.3
Bransford Bridgewind farm18refused6.4
Harborough Fields Farmsolar farm27permission expired6.6
Lentons Lane, Aldermans Greensolar farm25refused6.6
Lentons Lanesolar farm25approved, not built6.7
Swift Wind Farm (Bransford Bridge)wind farm8refused on appeal7.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4234, -1.3617).