Solar, wind and battery projects near Rugby (CV23)
37 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV23 (Rugby): 4 are waiting for a planning decision, 18 approved but not yet running, 7 operational. The largest live scheme is Bungalow Farm, Smeaton Lane (60 MW battery storage, application submitted on 28 January 2025, no decision recorded), 8.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CV23
Projects of 1 MW and more (22)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Ling Hallsolar farm | solar farm | 7 | operationalupdated Aug 2022 | Jul 2014 | — | Aug 2022 | Rugby | 5.1 |
| Rugby Road, Kilsby - Rainsbrook Solar Farmsolar farm | solar farm | 13 | approved, not built may be out of dateupdated Apr 2023 | Jul 2022 | granted Apr 2023 | Apr 2023 | Rugby | 5.9 |
| Harborough Fields Farmsolar farm | solar farm | 27 | permission expiredupdated Jul 2022 | Jun 2020 | granted Mar 2021 | Jul 2022 | Rugby | 6.0 |
| Bransford Bridgewind farm | wind farm | 18 | refusedupdated Apr 2012 | Jun 2011 | refused Sep 2011 | Apr 2012 | Rugby | 6.3 |
| School Farmsolar farm | solar farm | 12 | refusedupdated Oct 2016 | Nov 2014 | refused Sep 2016 | Oct 2016 | Rugby | 7.0 |
| Swift Wind Farm (Bransford Bridge)wind farm | wind farm | 8 | refused on appealupdated Feb 2016 | Nov 2013 | refused Apr 2014 | Feb 2016 | Rugby | 7.1 |
| Redland Roof Tiles Ltdwind turbine | wind turbine | 2 | refusedupdated Dec 2014 | Aug 2014 | refused Nov 2014 | Dec 2014 | Harborough | 7.3 |
| Swift Wind Farmwind farm | wind farm | 8 | application withdrawnupdated Mar 2016 | Apr 2015 | — | Mar 2016 | Harborough | 7.9 |
| Lilbourne Wind Farmwind farm | wind farm | 10 | operationalupdated Apr 2015 | Oct 2009 | granted Jul 2012 | Apr 2015 | West Northamptonshire | 8.1 |
| Streetfield Farmsolar farm | solar farm | 18.3 | operationalupdated Feb 2023 | Feb 2019 | granted Jun 2019 | Feb 2023 | Rugby | 8.2 |
| Bungalow Farm, Smeaton Lanebattery storage | battery storage | 60 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Rugby | 8.4 |
| Bungalow Farm, Smeaton Lanebattery storage | battery storage | 60 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Rugby | 8.4 |
| M1 J18 Wind Turbineswind farm | wind farm | 4 | operationalupdated Jun 2015 | Sep 2011 | granted Feb 2013 | Jun 2015 | West Northamptonshire | 8.5 |
| Northfield House Solar Farmsolar farm | solar farm | 26 | operationalupdated Feb 2023 | Aug 2020 | granted Nov 2020 | Feb 2023 | Harborough | 8.5 |
| Highwood Farmrooftop solar | rooftop solar | 1.3 | permission expiredupdated Aug 2020 | Apr 2016 | granted Jun 2016 | Aug 2020 | Rugby | 8.5 |
| Yelvertoft Wind Farmwind farm | wind farm | 16 | operationalupdated Jan 2015 | May 2009 | granted Jul 2010 | Jan 2015 | West Northamptonshire | 8.7 |
| Swinford Wind Farmsolar farm | solar farm | 20 | under constructionupdated May 2022 | Dec 2019 | granted Dec 2021 | May 2022 | Harborough | 9.0 |
| Swinford Wind Farmwind farm | wind farm | 22 | operationalupdated Dec 2012 | Apr 2008 | granted Dec 2009 | Dec 2012 | Harborough | 9.1 |
| The A361, Ashby St Ledgers Solar Farmsolar farm | solar farm | 35 | application submittedupdated Oct 2025 | Aug 2025 | — | Oct 2025 | West Northamptonshire | 9.4 |
| Crick Solar Farmsolar farm | solar farm | 49.9 | approved, not builtupdated Jul 2024 | Jan 2023 | granted Jun 2024 | Jul 2024 | West Northamptonshire | 9.6 |
| Crick Roadsolar farm | solar farm | 49.9 | under constructionupdated May 2023 | Apr 2020 | granted Nov 2020 | May 2023 | West Northamptonshire | 9.7 |
| Grove Farm, Daventry Road Solar Farmsolar farm | solar farm | 1.8 | application submittedupdated Mar 2026 | Jan 2026 | — | Mar 2026 | West Northamptonshire | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (15)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Somers Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jul 2025 | May 2025 | granted Jul 2025 | Jul 2025 | Rugby | 0.7 |
| Barby Roadrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2022 | Jun 2022 | granted Jul 2022 | Jun 2022 | Rugby | 1.4 |
| The Queens Diamond Jubilee Centre, Bruce Williams Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Feb 2025 | Mar 2025 | Rugby | 1.6 |
| J Sainsburys, Dunchurch Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Rugby | 1.8 |
| Hi Speed Services, Haynes Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2024 | Sep 2024 | granted Nov 2024 | Nov 2024 | Rugby | 3.3 |
| Cosford Lanerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2021 | Nov 2021 | granted Jan 2022 | Dec 2021 | Rugby | 3.3 |
| Symmetry Park Energy Centrebattery storage | battery storage | — | under constructionupdated Feb 2023 | Aug 2021 | granted Oct 2021 | Feb 2023 | Rugby | 3.9 |
| Onley Park, Barby Solar Photovoltaic PV Generation Systemsolar farm | solar farm | 0.3 | approved, not builtupdated Jan 2022 | Nov 2021 | granted Dec 2021 | Jan 2022 | West Northamptonshire | 5.1 |
| Quartzelec Limited, Castle Mound Wayrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Dec 2022 | Sep 2022 | granted Dec 2022 | Dec 2022 | Rugby | 5.1 |
| Rugby Motorway Services, Leicester Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Apr 2024 | Apr 2024 | Rugby | 5.1 |
| Peri Limited, Market Harborough Roadrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Feb 2023 | Oct 2022 | granted Dec 2022 | Feb 2023 | Rugby | 5.9 |
| Harborough Fields Farmbattery storage | battery storage | — | permission expiredupdated Jul 2020 | Jun 2020 | granted Mar 2021 | Jul 2020 | Rugby | 6.0 |
| Daventry International Rail Freight Terminal, Dirft Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated Jun 2023 | Mar 2023 | granted Jun 2023 | Jun 2023 | West Northamptonshire | 7.4 |
| Daventry International Rail Freight Terminal, Dirft Driverooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2023 | Mar 2023 | granted Jun 2023 | May 2023 | West Northamptonshire | 7.4 |
| Daventry International Rail Freight Terminal, Dirft Driverooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2023 | Mar 2023 | granted Jun 2023 | May 2023 | West Northamptonshire | 7.4 |
Distance from the average position of the CV23 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 12 | 2 | 5 | 3 | 1 | 170 |
| Rooftop solar | 13 | 0 | 12 | 0 | 0 | 4.5 |
| Wind farm | 7 | 0 | 0 | 4 | 2 | 0 |
| Wind turbine | 1 | 0 | 0 | 0 | 1 | 0 |
| Battery storage | 4 | 2 | 1 | 0 | 0 | 120 |
MW in pipeline: pending, approved and under-construction capacity.
How Rugby decides solar, wind and battery applications
| Applications | Rugby | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 25 | 10,236 |
| Refused | 3 (12%) | 19% |
| Solar refused | 1 of 18 | 12% |
| Onshore wind refused | 2 of 2 | 45% |
| Battery storage refused | 0 of 5 | 16% |
| Median time from submission to decision | 12.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV23, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.