Crick Solar Farm (49.9 MW)

Crick Solar Farm is a 49.9 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 26 June 2024, not yet built; the record was last updated on 2 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
2 July 2024record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
27 January 2023Application submitted
26 June 2024Planning permission granted
26 June 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
2 July 2024
Operator or applicant
Voltalia UK
Planning authority
West Northamptonshire
Planning application reference
WND/2022/1084
Site area
54.9 ha
Address (REPD)
N/O Field View Cottage, Watling Street, Kilsby, Rugby
Council area (by location)
West Northamptonshire
Time to decision
74 weeks
REPD reference
13470

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Watford Lodgewind farm12.5operational3.1
Watford Gap Wind Farmwind farm10refused3.6
Crick Roadsolar farm49.9under construction3.6
The A361, Ashby St Ledgers Solar Farmsolar farm35application submitted3.7
Rugby Road, Kilsby - Rainsbrook Solar Farmsolar farm13approved, not built3.8
Crockwell Hill Solar Farmsolar farm6approved, not built4.0
Crockwell Hill Solar Farmsolar farm6application submitted4.0
Yelvertoft Wind Farmwind farm16operational5.1
Lilbourne Wind Farmwind farm10operational7.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3286, -1.1527).