Energy Projects Near You

Ling Hall (7 MW solar farm)

Ling Hall is a 7 MW solar farm project in Rugby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 5 May 2021; the record was last updated on 19 August 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7 MWsolar farm
operationalstatus in REPD
19 August 2022record last updated
Rugbycouncil area

Planning timeline

DateStage
2 July 2014Application submitted
5 May 2021Operational

Project details

Technology
solar farm
Capacity
7 MW
Status (REPD)
operational
Record last updated
19 August 2022
Operator or applicant
REG Solarpower/Veolia
Planning authority
Rugby
Planning application reference
RBC/14CM029
Address (REPD)
Ling Hall Quarry, Coalpit Lane, Lawford Heath, Rugby
Council area (by location)
Rugby
REPD reference
6484

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leamington Road, Princethorpe - Ash Tree Solar Photovoltaic Arrayssolar farm16.8approved, not built6.3
Bungalow Farm, Smeaton Lanebattery storage60application submitted7.6
Bungalow Farm, Smeaton Lanebattery storage60application submitted7.6
Harborough Fields Farmsolar farm27permission expired9.4
Bransford Bridgewind farm18refused9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3554, -1.3507).