Solar, wind and battery projects near Coventry (CV3)
60 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of CV3 (Coventry): 14 are waiting for a planning decision, 36 approved but not yet running, 2 operational. The largest live scheme is T Main Road, Ansty (200 MW battery storage, approved on 12 September 2024, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of CV3
Projects of 1 MW and more (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Lentons Lane, Aldermans Greensolar farm | solar farm | 25 | refusedupdated May 2026 | Oct 2025 | refused Apr 2026 | May 2026 | Coventry | 6.1 |
| Lentons Lanesolar farm | solar farm | 25 | approved, not builtupdated May 2026 | Oct 2025 | granted Jan 2026 | May 2026 | Coventry | 6.2 |
| Torrington Avenue Battery Storage Facilitybattery storage | battery storage | 30 | approved, not builtupdated Apr 2024 | Jan 2024 | granted Apr 2024 | Apr 2024 | Coventry | 6.4 |
| Lentons Lane Solar Farmsolar farm | solar farm | 30 | refusedupdated Apr 2024 | May 2023 | refused Mar 2024 | Apr 2024 | Coventry | 6.6 |
| Highwood Farmrooftop solar | rooftop solar | 1.3 | permission expiredupdated Aug 2020 | Apr 2016 | granted Jun 2016 | Aug 2020 | Rugby | 6.9 |
| Coventry National Grid Substationbattery storage | battery storage | 49.9 | operationalupdated Jul 2025 | Jul 2020 | granted Jan 2021 | Jul 2025 | Coventry | 7.1 |
| Leamington Road, Princethorpe - Ash Tree Solar Photovoltaic Arrayssolar farm | solar farm | 16.8 | approved, not builtupdated Dec 2025 | May 2024 | granted Aug 2025 | Dec 2025 | Rugby | 7.2 |
| Coventry National Grid Substation, Hawkesbury Hallbattery storage | battery storage | 98 | application submittedupdated Dec 2025 | Jul 2025 | — | Dec 2025 | Coventry | 7.2 |
| T Main Road, Anstybattery storage | battery storage | 200 | approved, not builtupdated Sep 2024 | Feb 2024 | granted Sep 2024 | Sep 2024 | Rugby | 7.6 |
| Tolldish Hall Farm, Parrotts Grovesolar farm | solar farm | 25 | under constructionupdated Sep 2025 | Oct 2022 | granted Aug 2023 | Sep 2025 | Rugby | 7.7 |
| Mcdonnell Drive, Exhallbattery storage | battery storage | 30 | approved, not builtupdated Nov 2025 | Jun 2025 | granted Oct 2025 | Nov 2025 | Nuneaton and Bedworth | 7.7 |
| Central Boulevard, Prologis Parkrooftop solar | rooftop solar | 1.6 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 | Coventry | 7.7 |
| Bungalow Farm, Smeaton Lanebattery storage | battery storage | 60 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Rugby | 8.7 |
| Bungalow Farm, Smeaton Lanebattery storage | battery storage | 60 | application submittedupdated Feb 2025 | Jan 2025 | — | Feb 2025 | Rugby | 8.7 |
| Tanners Lanebattery storage | battery storage | 30 | approved, not builtupdated Jul 2025 | Nov 2024 | granted Jun 2025 | Jul 2025 | Coventry | 8.7 |
| Hollyhurst Farm, Mile Tree Lanesolar farm | solar farm | 25.6 | application submittedupdated Mar 2025 | Dec 2024 | — | Mar 2025 | Nuneaton and Bedworth | 8.7 |
| Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage | battery storage | 49.9 | approved, not builtupdated Feb 2025 | Oct 2023 | granted Jan 2025 | Feb 2025 | Warwick | 9.0 |
| Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage | battery storage | 49.9 | application submitted may be out of dateupdated Feb 2025 | Jul 2024 | — | Feb 2025 | Warwick | 9.0 |
| Nailcote Farmsolar farm | solar farm | 18 | refusedupdated Feb 2015 | Jul 2014 | refused Nov 2014 | Feb 2015 | Solihull | 9.1 |
| Burton Green Farmbattery storage | battery storage | 100 | approved, not builtupdated Jul 2025 | Sep 2024 | granted Jul 2025 | Jul 2025 | Warwick | 9.2 |
| Hodgetts Lane, Berkswell - Electricity Storage Facilitybattery storage | battery storage | 49.9 | application submitted may be out of dateupdated Aug 2023 | Jul 2023 | — | Aug 2023 | Solihull | 9.4 |
| Broad Lanesolar farm | solar farm | 8.5 | refused on appealupdated Mar 2017 | Sep 2015 | refused Feb 2016 | Mar 2017 | Coventry | 9.4 |
| Ling Hallsolar farm | solar farm | 7 | operationalupdated Aug 2022 | Jul 2014 | — | Aug 2022 | Rugby | 9.5 |
| Benton Green Lanebattery storage | battery storage | 70 | application submittedupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Solihull | 9.7 |
| Beechwood Farm, Hodgetts Lanebattery storage | battery storage | 57 | approved, not builtupdated Jan 2025 | Apr 2023 | granted Jan 2025 | Jan 2025 | Solihull | 9.7 |
| Beechwood Farm, Hodgetts Lanebattery storage | battery storage | 57 | application submitted may be out of dateupdated Jan 2025 | Jul 2024 | — | Jan 2025 | Solihull | 9.7 |
| Newgate Coolliery Solar Farm & Battery Storagesolar farm | solar farm | 6 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Nuneaton and Bedworth | 9.8 |
| Newgate Coolliery Solar Farm & Battery Storagebattery storage | battery storage | 5 | application submitted may be out of dateupdated Jun 2024 | May 2024 | — | Jun 2024 | Nuneaton and Bedworth | 9.8 |
| Holly Lane Energy Park Solar Farm & Battery Storagebattery storage | battery storage | 75 | approved, not builtupdated Feb 2026 | Sep 2023 | granted Jan 2025 | Feb 2026 | Solihull | 10.0 |
| Little Beanit Farm, Balsall Commonbattery storage | battery storage | 200 | under constructionupdated Mar 2026 | Oct 2022 | granted Aug 2023 | Mar 2026 | Solihull | 10.0 |
Smaller schemes under 1 MW, mostly rooftop solar (30)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Alan Higgs Centre, Allard Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Dec 2024 | Feb 2025 | Coventry | 0.4 |
| Manor Park Primary School, Ulverscroft Roadrooftop solar | rooftop solar | 0.2 | application submitted | May 2026 | — | — | Coventry | 2.1 |
| Coventry Universityrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Coventry | 2.2 |
| Coventry University, Decarbonisation Scheme - The Hubrooftop solar | rooftop solar | — | approved, not builtupdated Feb 2025 | Oct 2024 | granted Nov 2024 | Feb 2025 | Coventry | 2.2 |
| Ree Automotive Uk, Siskin Driverooftop solar | rooftop solar | 0.6 | approved, not builtupdated Mar 2025 | Feb 2025 | granted Apr 2025 | Mar 2025 | Warwick | 2.2 |
| UKBIC, Rowley Roadrooftop solar | rooftop solar | — | application submitted may be out of dateupdated Sep 2023 | Aug 2023 | — | Sep 2023 | Warwick | 2.3 |
| Ravensdale Primary School, Ravensdale Roadrooftop solar | rooftop solar | 0.2 | application submitted | Jun 2026 | — | — | Coventry | 2.5 |
| Cycle Works Buildingrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Coventry | 2.7 |
| Sidney Stringer Academy, Primrose Hill Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Sep 2025 | Jan 2026 | Coventry | 3.0 |
| Skipworth Roadrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Mar 2022 | Feb 2022 | granted Mar 2022 | Mar 2022 | Coventry | 3.0 |
| Siskin Parkway East, Middlemarch Business Parkrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated Mar 2022 | Dec 2022 | granted Feb 2023 | Mar 2022 | Warwick | 3.0 |
| City College, Swanswell Streetrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Sep 2025 | Jan 2026 | Coventry | 3.1 |
| Canute Haulage Group, Siskin Parkway Eastrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jun 2024 | Jul 2024 | Warwick | 3.1 |
| Caludon castle school, Axholme Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Coventry | 3.1 |
| Sky Dome Solar Photovoltaicsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Aug 2021 | Jun 2021 | granted Jul 2021 | Aug 2021 | Coventry | 3.3 |
| Brose, Courtaulds Wayrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Coventry | 4.1 |
| Coventry Sports Foundation, Bell Green Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Jan 2025 | Mar 2025 | Coventry | 4.4 |
| Mercedes Benz Coventry, John Wigley Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2022 | Sep 2022 | granted Oct 2022 | Nov 2022 | Coventry | 4.9 |
| Moat House Leisure & Neighbourhood Centre, Winston Avenuerooftop solar | rooftop solar | 0.3 | application submittedupdated Nov 2024 | Sep 2024 | — | Nov 2024 | Coventry | 5.0 |
| Bowling Alley, Olivier Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Coventry | 5.6 |
| Batleys Plc, Gielgud Wayrooftop solar | rooftop solar | 0.1 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Coventry | 5.9 |
| Sainsburys, Draken Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Rugby | 6.5 |
| Sainsburys Supermarketsrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Feb 2026 | Mar 2026 | Rugby | 6.5 |
| Unit 1, Mallory Way, Longfordrooftop solar | rooftop solar | 0.3 | refusedupdated Nov 2022 | Aug 2022 | refused Nov 2022 | Nov 2022 | Nuneaton and Bedworth | 7.0 |
| Unit 13, Central Boulevard Solar photovoltaicsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Coventry | 7.7 |
| Unit 12, Central Boulevardrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Apr 2026 | Jan 2026 | granted Feb 2026 | Apr 2026 | Coventry | 7.7 |
| Automotive Trim Developments, Priory Millrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2024 | Apr 2024 | granted Jun 2024 | Jun 2024 | Coventry | 7.9 |
| Brose, Colliery Lane Northrooftop solar | rooftop solar | 0.6 | refusedupdated Jan 2025 | Oct 2024 | refused Nov 2024 | Jan 2025 | Nuneaton and Bedworth | 8.8 |
| Castle Farm Recreation Ground, Fishponds Roadrooftop solar | rooftop solar | — | approved, not builtupdated Apr 2025 | Feb 2025 | granted Apr 2025 | Apr 2025 | Warwick | 9.3 |
| Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | refusedupdated Apr 2026 | Oct 2025 | refused Jan 2026 | Apr 2026 | Warwick | 9.3 |
Distance from the average position of the CV3 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 2 | 3 | 1 | 4 | 98.4 |
| Rooftop solar | 31 | 4 | 24 | 0 | 2 | 9 |
| Battery storage | 19 | 8 | 9 | 1 | 1 | 1,222 |
MW in pipeline: pending, approved and under-construction capacity.
How Coventry decides solar, wind and battery applications
| Applications | Coventry | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 2 (9%) | 19% |
| Solar refused | 2 of 21 | 12% |
| Battery storage refused | 0 of 2 | 16% |
| Median time from submission to decision | 7.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near CV3, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.