T Main Road, Ansty (200 MW battery storage)

T Main Road, Ansty is a 200 MW battery storage project in Rugby, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 12 September 2024, not yet built; the record was last updated on 24 September 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

200 MWbattery storage
approved, not builtstatus in REPD
24 September 2024record last updated
Rugbycouncil area

Planning timeline

DateStage
12 February 2024Application submitted
12 September 2024Planning permission granted
11 September 2027Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
200 MW
Status (REPD)
approved, not built
Record last updated
24 September 2024
Operator or applicant
FRV Tyler Hill BESS 1 Ltd
Planning authority
Rugby
Planning application reference
R24/0010
Address (REPD)
Main Road, Ansty
Council area (by location)
Rugby
Time to decision
30 weeks
Name in REPD
T Main Road, Ansty - Battery Energy Storage System
REPD reference
16212

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lentons Lane Solar Farmsolar farm30refused2.1
Lentons Lane, Aldermans Greensolar farm25refused2.6
Lentons Lanesolar farm25approved, not built2.7
Tolldish Hall Farm, Parrotts Grovesolar farm25under construction2.9
Coventry National Grid Substation, Hawkesbury Hallbattery storage98application submitted3.3
Hollyhurst Farm, Mile Tree Lanesolar farm25.6application submitted3.4
Coventry National Grid Substationbattery storage49.9operational3.5
Bungalow Farm, Smeaton Lanebattery storage60application submitted4.4
Bungalow Farm, Smeaton Lanebattery storage60application submitted4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.447, -1.4141).