Energy Projects Near You

Hollyhurst Farm, Mile Tree Lane (25.6 MW solar farm)

Hollyhurst Farm, Mile Tree Lane is a 25.6 MW solar farm project in Nuneaton and Bedworth, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 20 December 2024, no decision recorded; the record was last updated on 17 March 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

25.6 MWsolar farm
application submittedstatus in REPD
17 March 2025record last updated
Nuneaton and Bedworthcouncil area

Planning timeline

DateStage
20 December 2024Application submitted

Project details

Technology
solar farm
Capacity
25.6 MW
Status (REPD)
application submitted
Record last updated
17 March 2025
Operator or applicant
Greenfield Energy Developments Limited
Planning authority
Rugby
Planning application reference
40703
Site area
27.0 ha
Address (REPD)
Hollyhurst Farm, Mile Tree Lane, Coventry
Council area (by location)
Nuneaton and Bedworth
Name in REPD
Hollyhurst Farm, Mile Tree Lane - Solar Panels
REPD reference
18318

Who decides

ApplicationsRugbyUK
Decided applications (solar, wind, battery)2510,236
Refused3 (12%)19%
Solar refused1 of 1812%
Onshore wind refused2 of 245%
Battery storage refused0 of 516%
Median time from submission to decision12.6 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tolldish Hall Farm, Parrotts Grovesolar farm25under construction1.1
Coventry National Grid Substation, Hawkesbury Hallbattery storage98application submitted1.6
Coventry National Grid Substationbattery storage49.9operational1.8
Lentons Lane Solar Farmsolar farm30refused2.3
Lentons Lanesolar farm25approved, not built2.6
Lentons Lane, Aldermans Greensolar farm25refused2.7
Mcdonnell Drive, Exhallbattery storage30approved, not built2.7
T Main Road, Anstybattery storage200approved, not built3.4
Newgate Coolliery Solar Farm & Battery Storagesolar farm6application submitted3.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4681, -1.4508).