Lentons Lane Solar Farm (30 MW)

Lentons Lane Solar Farm is a 30 MW solar farm project in Coventry, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 21 March 2024; the record was last updated on 2 April 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWsolar farm
refusedstatus in REPD
2 April 2024record last updated
Coventrycouncil area

Planning timeline

DateStage
30 May 2023Application submitted
21 March 2024Refused by the planning authority

Project details

Technology
solar farm
Capacity
30 MW
Status (REPD)
refused
Record last updated
2 April 2024
Operator or applicant
Coventry City Council
Planning authority
Coventry
Planning application reference
PL/2023/0001062/FULM
Site area
51.0 ha
Address (REPD)
Land At Lentons Lane, Coventry
Council area (by location)
Coventry
Time to decision
42 weeks
REPD reference
13503

Who decides

ApplicationsCoventryUK
Decided applications (solar, wind, battery)2310,236
Refused2 (9%)19%
Solar refused2 of 2112%
Battery storage refused0 of 216%
Median time from submission to decision7.0 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lentons Lane, Aldermans Greensolar farm25refused0.7
Lentons Lanesolar farm25approved, not built0.7
Tolldish Hall Farm, Parrotts Grovesolar farm25under construction1.3
Coventry National Grid Substation, Hawkesbury Hallbattery storage98application submitted1.4
Coventry National Grid Substationbattery storage49.9operational1.5
T Main Road, Anstybattery storage200approved, not built2.1
Hollyhurst Farm, Mile Tree Lanesolar farm25.6application submitted2.3
Mcdonnell Drive, Exhallbattery storage30approved, not built3.3
Newgate Coolliery Solar Farm & Battery Storagesolar farm6application submitted5.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.4474, -1.4454).