Winwick (12.3 MW wind farm)

Winwick is a 12.3 MW wind farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 June 2016; the record was last updated on 16 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12.3 MWwind farm
operationalstatus in REPD
16 August 2016record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
17 May 2010Application submitted
13 July 2012Refused by the planning authority
13 July 2012Planning permission granted
13 July 2012Appeal allowed
15 April 2015Construction started
30 June 2016Operational

Project details

Technology
wind farm
Capacity
12.3 MW
Status (REPD)
operational
Record last updated
16 August 2016
Operator or applicant
Blue Energy
Planning authority
West Northamptonshire
Planning application reference
DA/2010/0400
Appeal reference
APP/Y2810/A/11/2156527
Turbines
6
Address (REPD)
Land To North and West Of Winwick Warren, Cold Ashby Road, Winwick, Northampton, Northamptonshire, NN6
Council area (by location)
West Northamptonshire
Time to decision
113 weeks
REPD reference
4164

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Crick Roadsolar farm49.9under construction5.0
Watford Lodgewind farm12.5operational5.3
Yelvertoft Wind Farmwind farm16operational6.1
Solar Farm & Battery Storage at North of South Kilworth Roadsolar farm49.9approved, not built6.7
Crick Solar Farmsolar farm49.9approved, not built7.4
Watford Gap Wind Farmwind farm10refused7.8
Lilbourne Wind Farmwind farm10operational7.8
Kelmarsh Wind Farm (Resubmission)wind farm12.5operational8.1
Swinford Wind Farmsolar farm20under construction8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.3657, -1.0622).