Salcey Green Farm (5 MW solar farm)

Salcey Green Farm is a 5 MW solar farm project in Milton Keynes, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 10 July 2024; the record was last updated on 17 July 2024.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refusedstatus in REPD
17 July 2024record last updated
Milton Keynescouncil area

Planning timeline

DateStage
17 April 2024Application submitted
10 July 2024Refused by the planning authority

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused
Record last updated
17 July 2024
Operator or applicant
Salcey Green Farm
Planning authority
Milton Keynes
Planning application reference
24/00830/FUL
Site area
6.7 ha
Address (REPD)
Salcey Green Farm, Forest Road, Hanslope
Council area (by location)
Milton Keynes
Time to decision
12 weeks
Name in REPD
Salcey Green Farm - Solar Panels
REPD reference
15458

Earlier applications for this site

ApplicationMWSubmittedOutcome
Salcey Green Farm 23/01252/FUL512 June 2023withdrawn 3 August 2023

Who decides

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stonepit Farmsolar farm5operational1.3
Littlewood Farmsolar farm14operational2.2
M1 Wind Farmwind farm7.2operational3.2
Stoke Heights Wind Farmwind farm30application withdrawn3.6
Salcey Solar Farmsolar farm5operational5.1
Manor Farm (Horton)solar farm5operational5.2
Orchard Way Wind Farmwind farm15refused on appeal6.6
Preston, Deanery Solar Farmsolar farm27.8application submitted7.0
Yardley Road Solar Farmsolar farm40application submitted7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1398, -0.8302).