Energy Projects Near You

Littlewood Farm (14 MW solar farm)

Littlewood Farm is a 14 MW solar farm project in Milton Keynes, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2015; the record was last updated on 19 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14 MWsolar farm
operationalstatus in REPD
19 August 2015record last updated
Milton Keynescouncil area

Planning timeline

DateStage
4 June 2014Application submitted
3 October 2014Planning permission granted
15 November 2014Construction started
26 March 2015Operational

Project details

Technology
solar farm
Capacity
14 MW
Status (REPD)
operational
Record last updated
19 August 2015
Operator or applicant
3C Energy
Planning authority
Milton Keynes
Planning application reference
14/01227/FUL
Site area
33.0 ha
Address (REPD)
Land Nw of Littlewood Farm Tathall End Hanslope
Council area (by location)
Milton Keynes
Time to decision
17 weeks
REPD reference
2182

Who decides

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stoke Heights Wind Farmwind farm30application withdrawn1.6
Salcey Green Farmsolar farm5refused2.2
Stonepit Farmsolar farm5operational3.0
Salcey Solar Farmsolar farm5operational4.0
Orchard Way Wind Farmwind farm15refused on appeal4.6
The Kicklessolar farm5operational5.4
M1 Wind Farmwind farm7.2operational5.5
Manor Farm (Horton)solar farm5operational5.7
Yardley Road Solar Farmsolar farm40application submitted7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.1267, -0.8052).