Energy Projects Near You

Renewable energy projects in Milton Keynes

93 solar, wind or battery projects of 150 kW or more are located in Milton Keynes (REPD, July 2026 extract): 5 pending, 57 approved but not running, 13 operational and 10 refused. The council refused 10 of 77 decided applications (13%; UK 19%), with a median 8 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

93projects in the council area
5awaiting a decision
57approved, not running
13%of decisions refused

How Milton Keynes decides

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

Projects in Milton Keynes

Projects of 1 MW and more (17)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Stoke Heights Wind Farmwind farmwind farm30application withdrawnupdated Feb 2018Jun 2011—Feb 2018
Nunn Woodwind farmwind farm24application withdrawnupdated Oct 2013——Oct 2013
Orchard Way Wind Farmwind farmwind farm15refused on appealupdated Aug 2014Sep 2011refused Nov 2012Aug 2014
Littlewood Farmsolar farmsolar farm14operationalupdated Aug 2015Jun 2014granted Oct 2014Aug 2015
Milton Keynes Wind Farmwind farmwind farm14operationalupdated Dec 2017Aug 2006granted Jan 2008Dec 2017
Rectory Farm/Embertonsolar farmsolar farm9operationalupdated Apr 2015Feb 2014granted Sep 2014Apr 2015
Salcey Solar Farmsolar farmsolar farm5operationalupdated Jul 2018Dec 2013granted Mar 2014Jul 2018
The Kicklessolar farmsolar farm5operationalupdated Apr 2016May 2014granted Nov 2014Apr 2016
Hyde Farmsolar farmsolar farm5operationalupdated Apr 2017Aug 2015granted Jan 2016Apr 2017
Salcey Green Farmsolar farmsolar farm5refusedupdated Jul 2024Apr 2024refused Jul 2024Jul 2024
Mercedes Benz UK Solar array car portrooftop solarrooftop solar2approved, not built may be out of dateupdated Dec 2021Jun 2021granted Sep 2021Dec 2021
Harvie Card Wayrooftop solarrooftop solar2operationalupdated Dec 2021Jun 2021granted Oct 2021Dec 2021
Chippenham Drive, Kingstonrooftop solarrooftop solar1.8approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024
Delico, Steinbeck Crescentrooftop solarrooftop solar1.6approved, not built may be out of dateupdated May 2023Jan 2023granted Apr 2023May 2023
Pendeen Crescent, Snelshall Eastrooftop solarrooftop solar1.2application submitted may be out of dateupdated Apr 2024Apr 2024—Apr 2024
DHL Supply Chain, Pendeen Crescent -Solar Panelsrooftop solarrooftop solar1.2approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024
Salcey Solar Farmbattery storagebattery storage1operationalupdated Mar 2019Mar 2016—Mar 2019
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Ingram Content Group UK, Chapter Houserooftop solarrooftop solar1approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Brioche Pasquier, Garamonde Driverooftop solarrooftop solar0.9refusedupdated May 2024Mar 2024refused May 2024May 2024
A G Barr Plc, Crossley Driverooftop solarrooftop solar0.9approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024
Thornbury, West Ashlandrooftop solarrooftop solar0.9approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023
Northfield Drive, Northfield Solar Panlesrooftop solarrooftop solar0.8approved, not builtupdated Feb 2022Feb 2022granted Mar 2022Feb 2022
Volkswagen Group UK, Garamonde Driverooftop solarrooftop solar0.7approved, not builtupdated Dec 2025Sep 2024granted Jan 2025Dec 2025
Brioche Pasquier UK, Garamonde Drive Solar Canopiesrooftop solarrooftop solar0.6approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025
David Lloyd, Livingstone Driverooftop solarrooftop solar0.6approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023
Red Bull Racing, Bradbourne Driverooftop solarrooftop solar0.6operationalupdated Jul 2026Jan 2026granted Mar 2026Jul 2026
Midway Centre, Harding Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023May 2023granted Jul 2023Jun 2023
Bradwell Road, Loughton Lodgerooftop solarrooftop solar0.5approved, not builtupdated Jun 2022Apr 2022granted Jun 2022Jun 2022
Burners Lane, Kiln Farmrooftop solarrooftop solar0.5approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025
Sensient Flavours, Bilton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023Apr 2023granted May 2023Jun 2023
Delaware Drive, Tongwellrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Oct 2024granted Nov 2024Jan 2025
Gosh Foods, Maidstone Roadrooftop solarrooftop solar0.5approved, not builtupdated Mar 2023Dec 2022granted Feb 2023Mar 2023
Linford Wood Business Park, Linford Woodrooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024
Wolverton Swimming And Fitness Centre, Addington Avenuerooftop solarrooftop solar0.4approved, not builtupdated Dec 2025Sep 2025granted Oct 2025Dec 2025
The Milton Keynes Academy, Fulwoods Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026
Vodafone, Fingle Driverooftop solarrooftop solar0.3approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023
Home Farm, Bedford Road Solar Power Arraysolar farmsolar farm0.3refusedupdated Jun 2023Nov 2022refused May 2023Jun 2023
Red Bull Ford Powertrains, Rindt Building, Bradbourne Drive – Solar Panelsrooftop solarrooftop solar0.3operationalAug 2022granted Sep 2023—
Northfield Drive, Northfield Driverooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024
Falcon Projectbattery storagebattery storage0.3operationalupdated Oct 2018——Oct 2018
Red Bull Racing Wind Tunnel, Sherbourne Drive – Solar Panelsrooftop solarrooftop solar0.3under constructionMar 2024granted Apr 2026—
Dawson Road, Bletchleyrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022
Dawson Road, Bletchleyrooftop solarrooftop solar0.3application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021
Caldecote Farm - Storage & Distribution Unitrooftop solarrooftop solar0.3under constructionupdated Jan 2025Sep 2021granted Jul 2023Jan 2025
Deltic Avenue, Rooksleyrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Dawson Rentals Vans, Dawson Road Solar Carport Canopy & BESSrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024
Unit 2, Watling Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024
Glebe Farm All Through School, Burney Driverooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Feb 2025Apr 2025
Third Avenue, Bletchleyrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Aug 2025granted Nov 2025Dec 2025
The Hazeley Academyrooftop solarrooftop solar0.2operationalupdated Oct 2019Feb 2019granted May 2020Oct 2019
Sir Herbert Leon Academyrooftop solarrooftop solar0.2approved, not builtupdated Sep 2021Feb 2021granted Apr 2021Sep 2021
Fen Street- Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2022Mar 2022granted May 2022Apr 2022
Tanners Drive, Blakelandsrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023
St Leger Drive, Great Linford - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2025Nov 2024granted Feb 2025Apr 2025
Hodge Lea Lane, Hodge Leabattery storagebattery storage0.2refusedupdated Feb 2025Nov 2024refused Jan 2025Feb 2025
Paxton Crescent, Ackroyd Place - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Jan 2025Nov 2024—Jan 2025
Stone Hill Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Jan 2025Nov 2024—Jan 2025
Northfield Drive, Tongwell Street - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Apr 2025Dec 2024granted Feb 2025Apr 2025
Duckworth Court, Oldbrook Boulevard - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2025Dec 2024granted Mar 2025Apr 2025
The Church Of The Latterday Saints, The High Streetbattery storagebattery storage0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025
Mowbray Green, The Leys - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Feb 2025Dec 2024—Feb 2025
Fingle Drive, Grafton Streetbattery storagebattery storage0.2refusedupdated Apr 2025Nov 2024refused Mar 2025Apr 2025
Kelvin Drive - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025
Pear Tree Lane, Bleak Hall - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Apr 2025Nov 2024granted Feb 2025Apr 2025
Grafton Street, End Of Dunsby Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025
Paynes Drive & Linceslade Grove, Loughton - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Apr 2025Nov 2024refused Feb 2025Apr 2025
Yeomans Drive, Blakelands - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025
Wolverton Swimming & Fitness Centre, Addington Avenuebattery storagebattery storage0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025
Wolverton Road, Giffard Park Roundabout - Micro Energy Storagebattery storagebattery storage0.2application submittedupdated Feb 2025Feb 2025—Feb 2025
Olney Road, Harvey Drive - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025
Dukes Drive, Princes Way - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025
Brickhill Street, Lakeside Roundabout - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025
Alston Drive, Bradwell Abbey - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025
Saxon Street, Dawson Roadbattery storagebattery storage0.2application withdrawnupdated Jul 2025Jun 2025—Jul 2025
Standing Way -Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025
Brickhill Street, Heybridge Crescentbattery storagebattery storage0.2application withdrawnupdated Jul 2025May 2025—Jul 2025
Snelshall Street, Tattenhoebattery storagebattery storage0.2application withdrawnupdated Nov 2025Jul 2025—Nov 2025

16 more projects not listed (furthest or smallest).

Postcode districts in Milton Keynes

DistrictProjects within 10 kmPendingApprovedOperational
MK19876213
MK29375810
MK39996211
MK49956312
MK59866311
MK69446012
MK79575713
MK89566211
MK99345912
MK108845810
MK118055010
MK128755512
MK139666212
MK149956017
MK159446013
MK168835218
MK179475812
MK208945614
MK46312910

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Milton Keynes by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.