Energy Projects Near You

Solar, wind and battery projects near Milton Keynes (MK2)

93 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of MK2 (Milton Keynes): 7 are waiting for a planning decision, 58 approved but not yet running, 10 operational. The largest live scheme is Oaks Farm Solar Farm (37 MW solar farm, approved on 29 May 2026, not yet built), 9.1 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

93projects within 10 km
7awaiting a decision
58approved, not running
10operational

Projects within 10 km of MK2

Projects of 1 MW and more (18)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
DHL Supply Chain, Pendeen Crescent -Solar Panelsrooftop solarrooftop solar1.2approved, not builtupdated Aug 2024Jun 2024granted Jul 2024Aug 2024Milton Keynes4.0
Pendeen Crescent, Snelshall Eastrooftop solarrooftop solar1.2application submitted may be out of dateupdated Apr 2024Apr 2024—Apr 2024Milton Keynes4.0
Salden Wind Farmwind farmwind farm10refusedupdated Sep 2015Dec 2013refused Aug 2015Sep 2015Buckinghamshire4.5
Delico, Steinbeck Crescentrooftop solarrooftop solar1.6approved, not built may be out of dateupdated May 2023Jan 2023granted Apr 2023May 2023Milton Keynes4.5
Dorcas Lane Wind Farmwind farmwind farm10refusedupdated Dec 2014Dec 2012refused Mar 2013Dec 2014Buckinghamshire5.2
Prospect Farmsolar farmsolar farm1.2permission expiredupdated Aug 2018Mar 2015granted Jun 2015Aug 2018Buckinghamshire5.4
Chippenham Drive, Kingstonrooftop solarrooftop solar1.8approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Milton Keynes6.1
Harvie Card Wayrooftop solarrooftop solar2operationalupdated Dec 2021Jun 2021granted Oct 2021Dec 2021Milton Keynes7.4
Checkley Wood Farmwind turbinewind turbine4.1operationalupdated Jan 2024Apr 2016granted Sep 2017Jan 2024Central Bedfordshire7.5
Double Arches Quarry Wind Turbinewind turbinewind turbine1.5operationalupdated Feb 2017Sep 2010granted Aug 2011Feb 2017Central Bedfordshire7.6
Eastern Waysolar farmsolar farm20application submittedMay 2026——Central Bedfordshire7.6
Eastern Waywind farmwind farm8.2application submittedMay 2026——Central Bedfordshire7.6
Double Arches Solar Arraysolar farmsolar farm2.5operationalupdated Sep 2020May 2020granted Nov 2020Sep 2020Central Bedfordshire7.6
Mercedes Benz UK Solar array car portrooftop solarrooftop solar2approved, not built may be out of dateupdated Dec 2021Jun 2021granted Sep 2021Dec 2021Milton Keynes8.2
Wood End, Mursley Roadsolar farmsolar farm36approved, not built may be out of dateupdated May 2022Jan 2020granted Dec 2022May 2022Buckinghamshire8.6
Oaks Farm Solar Farmsolar farmsolar farm37approved, not builtupdated Jul 2026Jul 2025granted May 2026Jul 2026Buckinghamshire9.1
Smarter Network Storagebattery storagebattery storage6decommissionedupdated Oct 2018——Oct 2018Central Bedfordshire9.6
Land At Potash Farmsolar farmsolar farm7operationalupdated Sep 2015Feb 2011granted Apr 2011Sep 2015Buckinghamshire9.9
Smaller schemes under 1 MW, mostly rooftop solar (60)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Premier Academy, Saffron Streetrooftop solarrooftop solar—approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Milton Keynes0.2
Dukes Drive, Princes Way - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated May 2025Jan 2025granted Mar 2025May 2025Milton Keynes0.8
Sir Herbert Leon Academyrooftop solarrooftop solar0.2approved, not builtupdated Sep 2021Feb 2021granted Apr 2021Sep 2021Milton Keynes1.1
Belvedere Lane, Watling Street - Micro Energy Storagebattery storagebattery storage0.2application submittedApr 2026——Milton Keynes1.3
Unit 2, Watling Streetrooftop solarrooftop solar0.2approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Milton Keynes1.5
Sensient Flavours, Bilton Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023Apr 2023granted May 2023Jun 2023Milton Keynes1.6
Strangford Drive, Skene Close - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026Milton Keynes1.6
Third Avenue, Bletchleyrooftop solarrooftop solar0.2approved, not builtupdated Dec 2025Aug 2025granted Nov 2025Dec 2025Milton Keynes1.6
Strangford Drive, Drayton Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2026Nov 2025granted Jan 2026Feb 2026Milton Keynes1.7
Watling Street - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025Jul 2025granted Aug 2025Nov 2025Milton Keynes1.9
Whaddon Way, Shenley Road - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Dec 2025Oct 2025refused Dec 2025Dec 2025Milton Keynes2.0
Dawson Road, Bletchleyrooftop solarrooftop solar0.3application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021Milton Keynes2.1
Dawson Road, Bletchleyrooftop solarrooftop solar0.3approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022Milton Keynes2.2
Dawson Rentals Vans, Dawson Road Solar Carport Canopy & BESSrooftop solarrooftop solar0.3approved, not builtupdated Jun 2024Apr 2024granted May 2024Jun 2024Milton Keynes2.2
Saxon Street, Dawson Roadbattery storagebattery storage0.2application withdrawnupdated Jul 2025Jun 2025—Jul 2025Milton Keynes2.2
Thornbury, West Ashlandrooftop solarrooftop solar0.9approved, not builtupdated Apr 2023Jan 2023granted Mar 2023Apr 2023Milton Keynes2.7
Brickhill Street, Heybridge Crescentbattery storagebattery storage0.2application withdrawnupdated Jul 2025May 2025—Jul 2025Milton Keynes2.7
Red Bull Racing, Bradbourne Driverooftop solarrooftop solar0.6operationalupdated Jul 2026Jan 2026granted Mar 2026Jul 2026Milton Keynes3.0
Grafton Street, End Of Dunsby Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025Milton Keynes3.0
Red Bull Racing Wind Tunnel, Sherbourne Drive – Solar Panelsrooftop solarrooftop solar0.3under constructionMar 2024granted Apr 2026—Milton Keynes3.1
Langland Road, Netherfield - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Feb 2026Nov 2025refused Jan 2026Feb 2026Milton Keynes3.2
Red Bull Ford Powertrains, Rindt Building, Bradbourne Drive – Solar Panelsrooftop solarrooftop solar0.3operationalAug 2022granted Sep 2023—Milton Keynes3.2
Pear Tree Lane, Bleak Hall - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Apr 2025Nov 2024granted Feb 2025Apr 2025Milton Keynes4.0
The Venue MK, Hindhead Knoll - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Dec 2025Oct 2025granted Dec 2025Dec 2025Milton Keynes4.1
Verge In Woughton Leisure Centre - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Jan 2026Oct 2025granted Dec 2025Jan 2026Milton Keynes4.5
Winterhill Houserooftop solarrooftop solar0.2approved, not builtupdated Nov 2021Sep 2021granted Nov 2021Nov 2021Milton Keynes4.6
Kelvin Drive - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Milton Keynes4.6
The Milton Keynes Academy, Fulwoods Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Nov 2025granted Dec 2025Jan 2026Milton Keynes4.6
Hammerwood Gate, By University Roundabout - Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Mar 2026Dec 2025granted Jan 2026Mar 2026Milton Keynes4.7
Paxton Crescent, Ackroyd Place - Micro Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Jan 2025Nov 2024—Jan 2025Milton Keynes4.9
Duckworth Court, Oldbrook Boulevard - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2025Dec 2024granted Mar 2025Apr 2025Milton Keynes5.0
Snelshall Street, Tattenhoebattery storagebattery storage0.2application withdrawnupdated Nov 2025Jul 2025—Nov 2025Milton Keynes5.2
Standing Way -Micro Energy Storagebattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Milton Keynes5.3
Mowbray Green, The Leys - Micro Energy Storagebattery storagebattery storage0.2application withdrawnupdated Feb 2025Dec 2024—Feb 2025Milton Keynes5.4
Midway Centre, Harding Roadrooftop solarrooftop solar0.5approved, not builtupdated Jun 2023May 2023granted Jul 2023Jun 2023Milton Keynes5.6
Glebe Farm All Through School, Burney Driverooftop solarrooftop solar0.2approved, not builtupdated Apr 2025Jan 2025granted Feb 2025Apr 2025Milton Keynes5.8
Falcon Projectbattery storagebattery storage0.3operationalupdated Oct 2018——Oct 2018Milton Keynes6.1
Blum Ukrooftop solarrooftop solar—operationalupdated Aug 2023——Aug 2023Milton Keynes6.1
Paynes Drive & Linceslade Grove, Loughton - Micro Energy Storage Facilitybattery storagebattery storage0.2refusedupdated Apr 2025Nov 2024refused Feb 2025Apr 2025Milton Keynes6.3
Gosh Foods, Maidstone Roadrooftop solarrooftop solar0.5approved, not builtupdated Mar 2023Dec 2022granted Feb 2023Mar 2023Milton Keynes6.3
A G Barr Plc, Crossley Driverooftop solarrooftop solar0.9approved, not builtupdated Jan 2024Oct 2023granted Dec 2023Jan 2024Milton Keynes6.3
Bradwell Road, Loughton Lodgerooftop solarrooftop solar0.5approved, not builtupdated Jun 2022Apr 2022granted Jun 2022Jun 2022Milton Keynes6.7
The Hazeley Academyrooftop solarrooftop solar0.2operationalupdated Oct 2019Feb 2019granted May 2020Oct 2019Milton Keynes6.8
Brickhill Street, Lakeside Roundabout - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Milton Keynes6.8
Bradwell Road - Micro Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2026Nov 2025granted Jan 2026Jan 2026Milton Keynes6.8
Deltic Avenue, Rooksleyrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Milton Keynes6.8
Northfield Drive, Northfield Driverooftop solarrooftop solar0.3approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Milton Keynes6.9
Fen Street- Solar Panelsrooftop solarrooftop solar0.2approved, not builtupdated Apr 2022Mar 2022granted May 2022Apr 2022Milton Keynes6.9
David Lloyd, Livingstone Driverooftop solarrooftop solar0.6approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Milton Keynes7.0
Northfield Drive, Tongwell Street - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Apr 2025Dec 2024granted Feb 2025Apr 2025Milton Keynes7.0
Northfield Drive, Northfield Solar Panlesrooftop solarrooftop solar0.8approved, not builtupdated Feb 2022Feb 2022granted Mar 2022Feb 2022Milton Keynes7.1
The Church Of The Latterday Saints, The High Streetbattery storagebattery storage0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Milton Keynes7.2
Volkswagen Group UK, Garamonde Driverooftop solarrooftop solar0.7approved, not builtupdated Dec 2025Sep 2024granted Jan 2025Dec 2025Milton Keynes7.5
Stone Hill Energy Storage Facilitybattery storagebattery storage0.2application withdrawnupdated Jan 2025Nov 2024—Jan 2025Milton Keynes7.6
Eastern Waybattery storagebattery storage—application submittedMay 2026——Central Bedfordshire7.6
Linford Wood Business Park, Linford Woodrooftop solarrooftop solar0.4approved, not builtupdated Apr 2024Feb 2024granted Mar 2024Apr 2024Milton Keynes7.8
Brioche Pasquier, Garamonde Driverooftop solarrooftop solar0.9refusedupdated May 2024Mar 2024refused May 2024May 2024Milton Keynes7.8
Alston Drive, Bradwell Abbey - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Nov 2025May 2025granted Jul 2025Nov 2025Milton Keynes7.8
Leighton Linslade Water Recycling Centresolar farmsolar farm0.5approved, not builtupdated Jan 2024Nov 2023granted Dec 2023Jan 2024Central Bedfordshire8.0
Brioche Pasquier UK, Garamonde Drive Solar Canopiesrooftop solarrooftop solar0.6approved, not builtupdated Feb 2025Oct 2024granted Jan 2025Feb 2025Milton Keynes8.0

15 more projects not listed (furthest or smallest).

Distance from the average position of the MK2 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8142093.7
Rooftop solar463355320.7
Wind farm310028.2
Wind turbine200200
Battery storage34219154

MW in pipeline: pending, approved and under-construction capacity.

How Milton Keynes decides solar, wind and battery applications

ApplicationsMilton KeynesUK
Decided applications (solar, wind, battery)7710,236
Refused10 (13%)19%
Solar refused4 of 4912%
Onshore wind refused1 of 245%
Battery storage refused5 of 2616%
Median time from submission to decision7.9 weeks17.0 weeks
Appeals lodged / allowed0 / 0—

All projects in Milton Keynes

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near MK2, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.