Energy Projects Near You

Smarter Network Storage (6 MW)

Smarter Network Storage is a 6 MW battery storage project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: decommissioned; the record was last updated on 23 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6 MWbattery storage
decommissionedstatus in REPD
23 October 2018record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
15 May 2014Construction started
12 December 2014Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
6 MW
Status (REPD)
decommissioned
Record last updated
23 October 2018
Operator or applicant
UK Power Networks
Planning authority
Central Bedfordshire
Planning application reference
not recorded
Address (REPD)
Leighton Buzzard, Bedfordshire
Council area (by location)
Central Bedfordshire
REPD reference
6863

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leighton Road & Hawthornsolar farm20approved, not built2.5
Manor Farmsolar farm5operational3.0
Grounds Farm Solar farmsolar farm20approved, not built3.9
Eastern Waywind farm8.2application submitted4.2
Eastern Waysolar farm20application submitted4.2
Bury Farm Solar Farmsolar farm49.9approved, not built4.2
Ledburn, Mentmore Solar Farmsolar farm49.9approved, not built4.3
Trinity Hall Solar Farmsolar farm15under construction4.5
Oakwood Farmsolar farm5abandoned4.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9166, -0.6528).