Energy Projects Near You

Leighton Road & Hawthorn (20 MW solar farm)

Leighton Road & Hawthorn is a 20 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 29 July 2025, not yet built; the record was last updated on 17 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
approved, not builtstatus in REPD
17 June 2026record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
28 February 2023Application submitted
29 July 2025Planning permission granted
29 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
approved, not built
Record last updated
17 June 2026
Operator or applicant
Econergy International Limited
Planning authority
Central Bedfordshire
Planning application reference
CB/22/04934/FULL
Site area
32.5 ha
Address (REPD)
North of Leighton Road and West of Hawthorn
Council area (by location)
Central Bedfordshire
Time to decision
126 weeks
Name in REPD
Leighton Road & Hawthorn - Solar Panels
REPD reference
12613

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farmsolar farm5operational0.7
Grounds Farm Solar farmsolar farm20approved, not built1.7
Trinity Hall Solar Farmsolar farm15under construction2.0
Tilsworthsolar farm20.3application withdrawn2.2
Smarter Network Storagebattery storage6decommissioned2.5
Bury Farm, Dickens Lanebattery storage350refused3.1
Eastern Waysolar farm20application submitted3.8
Eastern Waywind farm8.2application submitted3.8
Bury Farm Solar Farmsolar farm49.9approved, not built4.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9197, -0.6169).