Manor Farm (5 MW solar farm)

Manor Farm is a 5 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 27 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
27 August 2015record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
18 August 2014Application submitted
23 January 2015Planning permission granted
1 March 2015Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
27 August 2015
Operator or applicant
Lightsource Renewable Energy
Planning authority
Central Bedfordshire
Planning application reference
CB/14/03113/FULL
Site area
17.8 ha
Address (REPD)
Land north of Leighton Road, Eggington, Leighton Buzzard
Council area (by location)
Central Bedfordshire
Time to decision
23 weeks
REPD reference
2181

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Leighton Road & Hawthornsolar farm20approved, not built0.7
Grounds Farm Solar farmsolar farm20approved, not built1.1
Trinity Hall Solar Farmsolar farm15under construction1.9
Tilsworthsolar farm20.3application withdrawn2.2
Smarter Network Storagebattery storage6decommissioned3.0
Bury Farm, Dickens Lanebattery storage350refused3.1
Eastern Waywind farm8.2application submitted3.4
Eastern Waysolar farm20application submitted3.4
Bury Farm Solar Farmsolar farm49.9approved, not built5.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9248, -0.6118).