Trinity Hall Solar Farm (15 MW)

Trinity Hall Solar Farm is a 15 MW solar farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: under construction since 1 February 2025; the record was last updated on 27 January 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWsolar farm
under constructionstatus in REPD
27 January 2026record last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
11 February 2021Application submitted
5 May 2021Planning permission granted
9 August 2021Refused by the planning authority
1 February 2025Construction started

Project details

Technology
solar farm
Capacity
15 MW
Status (REPD)
under construction
Record last updated
27 January 2026
Operator or applicant
European Energy Photovoltaics Limited
Planning authority
Central Bedfordshire
Planning application reference
CB/21/00437/FULL
Site area
30.1 ha
Address (REPD)
N/O Stanbridge Road, Tilsworth, Leighton Buzzard
Council area (by location)
Central Bedfordshire
Time to decision
12 weeks
Contracts for Difference
AR6
REPD reference
12623

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Tilsworthsolar farm20.3application withdrawn0.3
Bury Farm, Dickens Lanebattery storage350refused1.2
Manor Farmsolar farm5operational1.9
Leighton Road & Hawthornsolar farm20approved, not built2.0
Grounds Farm Solar farmsolar farm20approved, not built2.1
Smarter Network Storagebattery storage6decommissioned4.5
Chalgrave Manorsolar farm24.6abandoned4.9
Eastern Waywind farm8.2application submitted5.1
Eastern Waysolar farm20application submitted5.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9161, -0.5879).