Energy Projects Near You

Eastern Way (8.2 MW wind farm)

Eastern Way is an 8.2 MW wind farm project in Central Bedfordshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 15 May 2026, no decision recorded; the record was last updated on an unrecorded date.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWwind farm
application submittedstatus in REPD
not recordedrecord last updated
Central Bedfordshirecouncil area

Planning timeline

DateStage
15 May 2026Application submitted

Project details

Technology
wind farm
Capacity
8.2 MW
Status (REPD)
application submitted
Record last updated
not recorded
Operator or applicant
Arnold White Estates Limited
Planning authority
Central Bedfordshire
Planning application reference
CB/26/01392/OUT
Turbines
2
Address (REPD)
Eastern Way, Heath And Reach, Leighton Buzzard
Council area (by location)
Central Bedfordshire
REPD reference
20963

Who decides

ApplicationsCentral BedfordshireUK
Decided applications (solar, wind, battery)5910,236
Refused8 (14%)19%
Solar refused4 of 3612%
Onshore wind refused2 of 745%
Battery storage refused2 of 1616%
Median time from submission to decision19.6 weeks17.0 weeks
Appeals lodged / allowed1 / 3—

Other large projects within 10 km

ProjectTypeMWStatuskm
Eastern Waysolar farm20application submitted<0.1
Grounds Farm Solar farmsolar farm20approved, not built3.0
Manor Farmsolar farm5operational3.4
Leighton Road & Hawthornsolar farm20approved, not built3.8
Smarter Network Storagebattery storage6decommissioned4.2
Trinity Hall Solar Farmsolar farm15under construction5.1
Tilsworthsolar farm20.3application withdrawn5.4
Bury Farm, Dickens Lanebattery storage350refused6.3
Dorcas Lane Wind Farmwind farm10refused7.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9522, -0.6332).