Energy Projects Near You

Oakwood Farm (5 MW solar farm)

Oakwood Farm is a 5 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: abandoned; the record was last updated on 25 October 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
abandonedstatus in REPD
25 October 2016record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
5 March 2014Application submitted
5 December 2014Planning permission granted
5 December 2017Permission expired

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
abandoned
Record last updated
25 October 2016
Operator or applicant
Bowler Energy
Planning authority
Buckinghamshire
Planning application reference
14/00615/APP
Site area
10.8 ha
Address (REPD)
Oakwood Farm Ledburn Mentmore Buckinghamshire
Council area (by location)
Buckinghamshire
Time to decision
39 weeks
REPD reference
1929

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ledburn, Mentmore Solar Farmsolar farm49.9approved, not built0.3
Bury Farm Solar Farmsolar farm49.9approved, not built2.2
Church Farmsolar farm6.2operational3.1
Great Seabrook Farmsolar farm5operational3.7
Smarter Network Storagebattery storage6decommissioned4.5
Straws Hadley Solar Farmsolar farm49.9approved, not built4.7
Leighton Road & Hawthornsolar farm20approved, not built6.1
Folly Farmsolar farm13.1operational6.1
Manor Farmsolar farm5operational6.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.8785, -0.6763).