Renewable energy projects in Buckinghamshire

101 solar, wind or battery projects of 150 kW or more are located in Buckinghamshire (REPD, July 2026 extract): 17 pending, 44 approved but not running, 18 operational and 11 refused. The council refused 19 of 80 decided applications (24%; UK 19%), with a median 15 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

101projects in the council area
17awaiting a decision
44approved, not running
24%of decisions refused

How Buckinghamshire decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Projects in Buckinghamshire

Projects of 1 MW and more (59)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
East Claydon Battery Energy Storagebattery storagebattery storage500approved, not builtupdated Sep 2025Dec 2023refused Dec 2024Sep 2025
East Claydon Substation, East Claydon Roadbattery storagebattery storage500application submittedupdated Jul 2025Apr 2025—Jul 2025
Mop End Farm, Mop End Lanebattery storagebattery storage500application submittedupdated Sep 2025Aug 2025—Sep 2025
Derehams Farm, Derehams Lanebattery storagebattery storage126application submitted may be out of dateupdated Dec 2023Nov 2023—Dec 2023
Hogshaw Road, Granboroughbattery storagebattery storage99application withdrawnupdated Apr 2025Dec 2024—Apr 2025
Stony Energy Storage Facilitybattery storagebattery storage79.9operationalupdated May 2024Jul 2017granted Sep 2021May 2024
Pinstone Farm, Oxford Roadbattery storagebattery storage60application submittedupdated Sep 2025Jul 2025—Sep 2025
Slough Roadbattery storagebattery storage57application withdrawnupdated Jan 2023Sep 2021—Jan 2023
Thornton Estatesolar farmsolar farm50application submittedupdated Sep 2025Jul 2025—Sep 2025
Whirlbush Farm, Kingsey Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Jul 2021granted Mar 2022Apr 2022
Bury Farm Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Jan 2022Jun 2021granted Jul 2022Jan 2022
Callie's Solar Farmsolar farmsolar farm49.9approved, not built may be out of dateupdated Apr 2022Mar 2022granted Nov 2022Apr 2022
Ledburn, Mentmore Solar Farmsolar farmsolar farm49.9approved, not builtupdated Jan 2026Aug 2023refused Nov 2024Jan 2026
Straws Hadley Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Apr 2023granted Dec 2024Feb 2026
Longbreach Solar Farmsolar farmsolar farm49.9application submittedupdated Aug 2025Jun 2025—Aug 2025
Salters Lanesolar farmsolar farm42application submittedupdated Aug 2025Jul 2025—Aug 2025
Hale Solar Farmsolar farmsolar farm40application submitted may be out of dateupdated Feb 2026Mar 2020—Feb 2026
Derehams Farm, Derehams Lanebattery storagebattery storage40operationalupdated Feb 2026Nov 2022granted Jun 2023Feb 2026
Kimblewick Road Solar Farmsolar farmsolar farm40approved, not builtupdated Jan 2026Jul 2023granted Jan 2026Jan 2026
Oaks Farm Solar Farmsolar farmsolar farm37approved, not builtupdated Jul 2026Jul 2025granted May 2026Jul 2026
Wood End, Mursley Roadsolar farmsolar farm36approved, not built may be out of dateupdated May 2022Jan 2020granted Dec 2022May 2022
Lye Green Energy Storagebattery storagebattery storage25refused on appealupdated Jun 2019Jun 2018—Jun 2019
Tuckey Farmsolar farmsolar farm25approved, not built may be out of dateupdated Feb 2025Mar 2019granted Apr 2021Feb 2025
Manor Farm, Beachampton Solar Farmsolar farmsolar farm25approved, not builtupdated Apr 2026Oct 2022granted Jan 2024Apr 2026
Gib Lane (Aston Clinton solar park)solar farmsolar farm24.2operationalupdated Dec 2015Aug 2014granted Nov 2014Dec 2015
Moat Farm Solar Farmsolar farmsolar farm24.1approved, not built may be out of dateupdated Mar 2022Aug 2021granted Feb 2022Mar 2022
Fox Covert Solar Farmsolar farmsolar farm22operationalupdated Oct 2023Aug 2020granted Jun 2021Oct 2023
Gerrards Cross Sewage Treatment Worksbattery storagebattery storage20application submitted may be out of dateupdated Jan 2021Dec 2020—Jan 2021
Turweston Solar Farmsolar farmsolar farm16.7operationalupdated Mar 2015Jun 2013granted Sep 2013Mar 2015
Calvert Landfill Site Solar Arraysolar farmsolar farm16application submitted may be out of dateupdated Sep 2021Mar 2021—Sep 2021
Westcott Venture Park Solar Farmsolar farmsolar farm15abandonedupdated Jun 2019Jul 2014granted May 2017Jun 2019
Bumpers Lane Solar Farmbattery storagebattery storage13.3operationalupdated Dec 2021Nov 2016—Dec 2021
Bumpers Farm Phase 2solar farmsolar farm12approved, not built may be out of dateupdated Jun 2020Jul 2014granted Oct 2015Jun 2020
Manor Farmsolar farmsolar farm12approved, not built may be out of dateupdated Feb 2023Jan 2021granted Jun 2022Feb 2023
Salden Wind Farmwind farmwind farm10refusedupdated Sep 2015Dec 2013refused Aug 2015Sep 2015
Dorcas Lane Wind Farmwind farmwind farm10refusedupdated Dec 2014Dec 2012refused Mar 2013Dec 2014
Litchlake Farmbattery storagebattery storage10permission expiredupdated Apr 2020May 2017—Apr 2020
Littleton Green Energy Parksolar farmsolar farm10application submitted may be out of dateupdated Jul 2023Nov 2022—Jul 2023
Gawcott Fields Farmsolar farmsolar farm9.2operationalupdated Apr 2016Jul 2014granted Oct 2014Apr 2016
Knapps Hook Farmsolar farmsolar farm8.9application withdrawnupdated Sep 2014Jun 2014—Sep 2014
Forty Green Farmsolar farmsolar farm7.5refusedupdated Nov 2014Jan 2014refused Oct 2014Nov 2014
Coldmoorholme Lane Battery Storagebattery storagebattery storage7.2refusedupdated Dec 2021Dec 2020refused Sep 2021Dec 2021
Land At Potash Farmsolar farmsolar farm7operationalupdated Sep 2015Feb 2011granted Apr 2011Sep 2015
Church Farmsolar farmsolar farm6.2operationalupdated Dec 2015Aug 2014granted Oct 2014Dec 2015
Littleton Green Energy Parkwind turbinewind turbine6.2application submitted may be out of dateupdated Jul 2023Nov 2022—Jul 2023
Great Seabrook Farmsolar farmsolar farm5operationalupdated Jul 2016Jun 2014granted Nov 2014Jul 2016
Oakwood Farmsolar farmsolar farm5abandonedupdated Oct 2016Mar 2014granted Dec 2014Oct 2016
Bumpers Farm Phase 1solar farmsolar farm5operationalupdated Jun 2017Jul 2014granted Oct 2015Jun 2017
Land at Thornborough Groundssolar farmsolar farm5operationalupdated Jul 2018Mar 2015granted Jun 2015Jul 2018
Gib Lane Solar farm (Extension)solar farmsolar farm5operationalupdated Jun 2016Jul 2015granted Oct 2015Jun 2016
Land North of Marlow Landfill Sitesolar farmsolar farm5refusedupdated Mar 2015Sep 2015refused Feb 2016Mar 2015
Stratford Road Solar Farmsolar farmsolar farm5approved, not built may be out of dateupdated Dec 2021Dec 2020granted Jan 2022Dec 2021
Long Meadow Farmsolar farmsolar farm4.1operationalupdated Jan 2016Sep 2013granted Jan 2014Jan 2016
Land Adjacent to A422solarsolar3.4application withdrawnupdated Feb 2014Oct 2013—Feb 2014
Land adjacent to A422solar farmsolar farm1.6application withdrawnupdated Feb 2015Nov 2014—Feb 2015
Quarrendon Fieldswind turbinewind turbine1.5operationalupdated Jan 2015Feb 2010granted Mar 2012Jan 2015
Westcott Venture Park Phase 2 & 3solar farmsolar farm1.3operationalupdated Nov 2012Feb 2011granted Jun 2011Nov 2012
Wipac Group, London Roadrooftop solarrooftop solar1.3approved, not builtupdated Jun 2026Apr 2026granted Jun 2026Jun 2026
Prospect Farmsolar farmsolar farm1.2permission expiredupdated Aug 2018Mar 2015granted Jun 2015Aug 2018
Smaller schemes under 1 MW, mostly rooftop solar (42)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Safren Power Uk Limitedrooftop solarrooftop solar1approved, not builtupdated Jun 2022May 2022granted Jul 2022Jun 2022
Silverstone Road, Biddlesdenrooftop solarrooftop solar0.9approved, not builtupdated Mar 2022Mar 2022granted Apr 2022Mar 2022
Hawes Recycling Centre, Coronation Roadrooftop solarrooftop solar0.7refusedupdated Feb 2025Nov 2024refused Feb 2025Feb 2025
Eden Shopping Centre, Oxford Road,rooftop solarrooftop solar0.6approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023
Aylesbury College Decarbonisationrooftop solarrooftop solar0.5approved, not builtupdated Oct 2025Jul 2025granted Sep 2025Oct 2025
Gatehouse Roadrooftop solarrooftop solar0.5approved, not builtupdated Sep 2023Aug 2023granted Sep 2023Sep 2023
Wycombe Leisure Centre, Handy Crossrooftop solarrooftop solar0.5approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025
The Whiteleaf Centre, Bierton Roadrooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Sep 2023granted Oct 2023Nov 2023
Thomas Road, Wooburn Industrial Estaterooftop solarrooftop solar0.4approved, not builtupdated Nov 2023Oct 2023granted Nov 2023Nov 2023
Beaconsfield Services, Windsor Roadrooftop solarrooftop solar0.4approved, not builtupdated Apr 2026Jan 2026granted Mar 2026Apr 2026
Haddenham Garden Centre, Stanbridge Roadrooftop solarrooftop solar0.4approved, not builtupdated Mar 2023Jan 2023granted Feb 2023Mar 2023
Bellingdon Brickworks, Chesham Roadrooftop solarrooftop solar0.3approved, not builtupdated Apr 2026Oct 2025granted Jan 2026Apr 2026
Denham Grove Hotel, Tilehouse Lanerooftop solarrooftop solar0.3refusedupdated Jun 2026Mar 2026refused May 2026Jun 2026
Aqua Vale Swimming and Fitness Centre, Park Streetrooftop solarrooftop solar0.3approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025
Liscombe Business Park - Ground Mounted Solar Arraysolar farmsolar farm0.3approved, not builtupdated Feb 2024May 2023granted Feb 2024Feb 2024
Fairhouse, Burnham Roadsolar farmsolar farm0.2refusedupdated Dec 2025Sep 2025refused Nov 2025Dec 2025
Brackley Sewage Treatment Works, Brackley Roadsolar farmsolar farm0.2approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022
Tims Dairy, Denham Lanerooftop solarrooftop solar0.2application submittedMay 2026——
Buckingham Tesco Superstorerooftop solarrooftop solar0.2operationalupdated Apr 2020Mar 2019granted Jul 2019Apr 2020
University Of Buckingham Campus, Energy Storage Systembattery storagebattery storage0.2application withdrawnupdated May 2023Mar 2023—May 2023
Crockmore Lane, Fawleysolar farmsolar farm0.2refusedupdated Aug 2025Dec 2024refused Jul 2025Aug 2025
Stablebridge Road, Aston Clintonbattery storagebattery storage0.2approved, not builtupdated Apr 2026Oct 2025granted Feb 2026Apr 2026
GE Healthcare, Pollards Woodrooftop solarrooftop solar0.2approved, not builtupdated May 2026Feb 2026granted Apr 2026May 2026
Addingrove Farm, Bicester Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Mar 2025granted May 2025Jun 2025
Big Yellow Self Storage, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024
Holmer Green Senior Schoolrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Jul 2024granted Sep 2024Nov 2024
The Swan Pool & Leisure Centre, London Roadrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Dec 2024granted Jan 2025Feb 2025
Noble Foods, Barton Roadrooftop solarrooftop solar0.2application submittedJun 2026——
Pitchcott Hill Farm, Pitchcott Hillrooftop solarrooftop solar0.2approved, not builtupdated Mar 2025Jan 2025granted Mar 2025Mar 2025
Newlands Meadow, Edenrooftop solarrooftop solar0.1approved, not builtupdated Jun 2022Jun 2022granted Aug 2022Jun 2022
Wings Poultry Farm, Stewkley Roadrooftop solarrooftop solar0.1refusedupdated Jan 2025Oct 2024refused Nov 2024Jan 2025
Faccenda Foods, Wellington Farmrooftop solarrooftop solar0.1application submittedupdated Feb 2025Jan 2025—Feb 2025
Church Farmbattery storagebattery storage—permission expiredupdated Aug 2020Oct 2017granted Mar 2019Aug 2020
Fox Covert Solar Farmbattery storagebattery storage—operationalupdated Oct 2023Aug 2020granted Jun 2021Oct 2023
Whirlbush Farm, Kingsey Solar Farm & Battery Storagebattery storagebattery storage—approved, not built may be out of dateupdated Apr 2022Jul 2021granted Mar 2022Apr 2022
Globe Business Park, Fieldhouse Lanerooftop solarrooftop solar—approved, not built may be out of dateupdated Feb 2023Oct 2022granted Jan 2023Feb 2023
Iver Water Treatment Works, Court Lanesolar farmsolar farm—approved, not built may be out of dateupdated Jun 2023May 2023granted Jul 2023Jun 2023
David Lloyd Leisure Grouprooftop solarrooftop solar—approved, not builtupdated Aug 2023Jun 2023granted Aug 2023Aug 2023
Holly Green Farm, Sandpit Lanerooftop solarrooftop solar—approved, not builtupdated Nov 2024Sep 2024granted Nov 2024Nov 2024
Salters Lanesolar farmsolar farm—application submittedupdated Aug 2025Jul 2025—Aug 2025
Salters Lanebattery storagebattery storage—application submittedupdated Aug 2025Jul 2025—Aug 2025
Rids Hill Farm, Wotton Roadrooftop solarrooftop solar—approved, not builtupdated Jul 2025Apr 2025granted Jun 2025Jul 2025

Postcode districts in Buckinghamshire

DistrictProjects within 10 kmPendingApprovedOperational
HP5142110
HP617591
HP7217111
HP82710102
HP9288141
HP10235112
HP11205101
HP1218681
HP1319591
HP149060
HP1519591
HP168150
HP17233135
HP18224115
HP19253147
HP20213135
HP21211146
HP22171106
HP2714193
MK18275128
SL0534364
SL722682
SL8276132
SL9309142
UB9295181

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Buckinghamshire by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.