Energy Projects Near You

Coldmoorholme Lane Battery Storage (7.2 MW)

Coldmoorholme Lane Battery Storage is a 7.2 MW battery storage project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 15 September 2021; the record was last updated on 10 December 2021.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.2 MWbattery storage
refusedstatus in REPD
10 December 2021record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
16 December 2020Application submitted
15 September 2021Refused by the planning authority

Project details

Technology
battery storage (stand-alone storage)
Capacity
7.2 MW
Status (REPD)
refused
Record last updated
10 December 2021
Operator or applicant
Envirotech Energy Solutions
Planning authority
Buckinghamshire
Planning application reference
20/08321/FUL
Address (REPD)
Btw Landfill Site
Council area (by location)
Buckinghamshire
Time to decision
39 weeks
REPD reference
8280

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land North of Marlow Landfill Sitesolar farm5refused1.5
Derehams Farm, Derehams Lanebattery storage126application submitted3.8
Derehams Farm, Derehams Lanebattery storage40operational3.8
Salters Lanesolar farm42application submitted4.6
Mop End Farm, Mop End Lanebattery storage500application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5837, -0.7254).