Land North of Marlow Landfill Site (5 MW solar farm)
Land North of Marlow Landfill Site is a 5 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 26 February 2016; the record was last updated on 4 March 2015.
5 MWsolar farm
refusedstatus in REPD
4 March 2015record last updated
Buckinghamshirecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 7 September 2015 | Application submitted |
| 26 February 2016 | Refused by the planning authority |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- refused
- Record last updated
- 4 March 2015
- Operator or applicant
- Anesco
- Planning authority
- Buckinghamshire
- Planning application reference
- 15/07001/FULEA
- Site area
- 13.2 ha
- Address (REPD)
- Ld N Of Marlow Landfill Site, Marlow Road, Little Marlow, Marlow
- Council area (by location)
- Buckinghamshire
- Time to decision
- 25 weeks
- REPD reference
- 5684
Who decides
| Applications | Buckinghamshire | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 80 | 10,236 |
| Refused | 19 (24%) | 19% |
| Solar refused | 14 of 68 | 12% |
| Onshore wind refused | 2 of 3 | 45% |
| Battery storage refused | 3 of 9 | 16% |
| Median time from submission to decision | 15.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 6 / 7 | — |
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Coldmoorholme Lane Battery Storage | battery storage | 7.2 | refused | 1.5 |
| Derehams Farm, Derehams Lane | battery storage | 126 | application submitted | 4.8 |
| Derehams Farm, Derehams Lane | battery storage | 40 | operational | 4.8 |
| Salters Lane | solar farm | 42 | application submitted | 6.1 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.5831, -0.7464).