Energy Projects Near You

Derehams Farm, Derehams Lane (40 MW battery storage)

Derehams Farm, Derehams Lane is a 40 MW battery storage project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 6 August 2025; the record was last updated on 13 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWbattery storage
operationalstatus in REPD
13 February 2026record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
14 November 2022Application submitted
29 June 2023Refused by the planning authority
29 June 2023Planning permission granted
19 February 2024Construction started
6 August 2025Operational

Project details

Technology
battery storage (stand-alone storage)
Capacity
40 MW
Status (REPD)
operational
Record last updated
13 February 2026
Operator or applicant
Eku Energy / Statkraft
Planning authority
Buckinghamshire
Planning application reference
22/08045/FUL
Address (REPD)
Derehams Farm, Derehams Lane, Loudwater, High Wycombe
Council area (by location)
Buckinghamshire
Time to decision
32 weeks
Name in REPD
Derehams Farm, Derehams Lane - Battery Storage
REPD reference
12803

Earlier applications for this site

ApplicationMWSubmittedOutcome
Loudwater Battery Storage Site 18/07600/FUL405 November 2018replaced by a revised application

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Derehams Farm, Derehams Lanebattery storage126application submitted<0.1
Salters Lanesolar farm42application submitted3.3
Coldmoorholme Lane Battery Storagebattery storage7.2refused3.8
Land North of Marlow Landfill Sitesolar farm5refused4.8
Mop End Farm, Mop End Lanebattery storage500application submitted6.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.6114, -0.694).