Turweston Solar Farm (16.7 MW)

Turweston Solar Farm is a 16.7 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 19 December 2014; the record was last updated on 19 March 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16.7 MWsolar farm
operationalstatus in REPD
19 March 2015record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
14 June 2013Application submitted
10 September 2013Planning permission granted
15 November 2013Construction started
19 December 2014Operational

Project details

Technology
solar farm
Capacity
16.7 MW
Status (REPD)
operational
Record last updated
19 March 2015
Operator or applicant
INRG Solar
Planning authority
Buckinghamshire
Planning application reference
13/01561/APP
Site area
35.0 ha
Address (REPD)
Turweston Aerodrome, Whitfield Road, Biddlesden, Buckinghamshire
Council area (by location)
Buckinghamshire
Time to decision
13 weeks
REPD reference
2081

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farm, Whitfieldsolar farm30application submitted2.0
Hall Farmsolar farm5.1operational4.0
Primrose Hill Farm, Oxford Road Solar Farmsolar farm24application submitted5.4
Shelswell Park Solar Farmsolar farm5operational6.6
Litchlake Farmbattery storage10permission expired6.7
Welsh Lanesolar farm30approved, not built6.9
Halse Road Solar Farm & Battery Storagesolar farm49.9approved, not built7.3
Spring Farm Ridgewind farm15refused7.4
Farthinghoe Solar Farmsolar farm10refused7.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0328, -1.1053).