Halse Road Solar Farm & Battery Storage (49.9 MW)

Halse Road Solar Farm & Battery Storage is a 49.9 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 14 November 2023, not yet built; the record was last updated on 29 March 2022.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
29 March 2022record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
10 March 2022Application submitted
26 October 2022Refused by the planning authority
13 February 2023Appeal lodged
14 November 2023Planning permission granted
14 November 2023Appeal allowed

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
29 March 2022
Operator or applicant
JBM Solar Projects Limited
Planning authority
West Northamptonshire
Planning application reference
WNS/2022/0557/EIA
Appeal reference
WNS/2022/0557/EIA
Site area
79.0 ha
Address (REPD)
Halse Road, south of Greatworth,
Council area (by location)
West Northamptonshire
Time to decision
88 weeks
Contracts for Difference
AR6
Name in REPD
Halse Road - Solar Farm & Battery Storage
REPD reference
10877

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Earlier applications for this site

ApplicationMWSubmittedOutcome
Greatworth Solar Farm & Battery Stations WNS/2021/0935/EIA49.929 June 2021withdrawn 2 December 2021

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Farthinghoe Solar Farmsolar farm10refused1.0
Welsh Lanesolar farm30approved, not built2.8
Hall Farmsolar farm5.1operational3.4
Spring Farm Ridgewind farm15refused3.5
Manor Farm, Whitfieldsolar farm30application submitted6.2
Turweston Solar Farmsolar farm16.7operational7.3
Primrose Hill Farm, Oxford Road Solar Farmsolar farm24application submitted9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0652, -1.199).