Energy Projects Near You

Solar, wind and battery projects near Brackley (NN13)

21 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of NN13 (West Northamptonshire): 4 are waiting for a planning decision, 8 approved but not yet running, 4 operational. The largest live scheme is Halse Road Solar Farm & Battery Storage (49.9 MW solar farm, approved on 14 November 2023, not yet built), 4.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

21projects within 10 km
4awaiting a decision
8approved, not running
4operational

Projects within 10 km of NN13

Projects of 1 MW and more (13)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land Adjacent to A422solarsolar3.4application withdrawnupdated Feb 2014Oct 2013—Feb 2014Buckinghamshire1.6
Hall Farmsolar farmsolar farm5.1operationalupdated Apr 2015Sep 2013granted Dec 2013Apr 2015West Northamptonshire2.1
Land adjacent to A422solar farmsolar farm1.6application withdrawnupdated Feb 2015Nov 2014—Feb 2015Buckinghamshire2.2
Turweston Solar Farmsolar farmsolar farm16.7operationalupdated Mar 2015Jun 2013granted Sep 2013Mar 2015Buckinghamshire2.9
Manor Farm, Whitfieldsolar farmsolar farm30application submittedupdated Jan 2025Dec 2024—Jan 2025West Northamptonshire3.1
Halse Road Solar Farm & Battery Storagesolar farmsolar farm49.9approved, not builtupdated Mar 2022Mar 2022granted Nov 2023Mar 2022West Northamptonshire4.9
Farthinghoe Solar Farmsolar farmsolar farm10refusedupdated Nov 2014Aug 2014refused Nov 2014Nov 2014West Northamptonshire5.1
Welsh Lanesolar farmsolar farm30approved, not built may be out of dateupdated Nov 2021Apr 2021granted Nov 2021Nov 2021West Northamptonshire5.4
Spring Farm Ridgewind farmwind farm15refusedupdated Aug 2016Oct 2010refused Jun 2011Aug 2016West Northamptonshire6.1
Shelswell Park Solar Farmsolar farmsolar farm5operationalupdated Feb 2014Feb 2011granted May 2011Feb 2014Cherwell7.1
Primrose Hill Farm, Oxford Road Solar Farmsolar farmsolar farm24application submittedupdated Jun 2025May 2025—Jun 2025West Northamptonshire7.4
Litchlake Farmbattery storagebattery storage10permission expiredupdated Apr 2020May 2017—Apr 2020Buckinghamshire9.0
Culworth House Solar Farmsolar farmsolar farm3operationalupdated Apr 2015Mar 2011granted Mar 2013Apr 2015West Northamptonshire9.2
Smaller schemes under 1 MW, mostly rooftop solar (8)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Sainsburys Supermarkets, Wellington Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2023Aug 2023granted Oct 2023Nov 2023West Northamptonshire0.8
Farm Road -Battery Energy Storagebattery storagebattery storage0.2application submittedupdated Sep 2024Aug 2024—Sep 2024West Northamptonshire0.9
Brackley Sewage Treatment Works, Brackley Roadsolar farmsolar farm0.2approved, not builtupdated Dec 2022Oct 2022granted Nov 2022Dec 2022Buckinghamshire2.2
Halse Road Solar Farm & Battery Storagebattery storagebattery storage—approved, not builtupdated Mar 2022Mar 2022granted Nov 2023Mar 2022West Northamptonshire4.9
Middle Farm, Featherbed Lanerooftop solarrooftop solar0.2approved, not builtupdated Jul 2025Mar 2025granted May 2025Jul 2025Cherwell5.7
Noble Foods, Barton Roadrooftop solarrooftop solar0.2application submittedJun 2026——Buckinghamshire8.7
Silverstone Road, Biddlesdenrooftop solarrooftop solar0.9approved, not builtupdated Mar 2022Mar 2022granted Apr 2022Mar 2022Buckinghamshire9.5
Moto Hospitality, Stoke Lynerooftop solarrooftop solar0.2approved, not builtupdated Apr 2024Feb 2024granted Apr 2024Apr 2024Cherwell10.0

Distance from the average position of the NN13 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm112341134
Rooftop solar514001.6
Solar100000
Wind farm100010
Battery storage311000.2

MW in pipeline: pending, approved and under-construction capacity.

How West Northamptonshire decides solar, wind and battery applications

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

All projects in West Northamptonshire

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near NN13, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.