Spring Farm Ridge (15 MW wind farm)

Spring Farm Ridge is a 15 MW wind farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 30 June 2011; the record was last updated on 1 August 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15 MWwind farm
refusedstatus in REPD
1 August 2016record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
19 October 2010Application submitted
30 June 2011Refused by the planning authority
11 April 2013Appeal lodged
23 December 2014Appeal refused
23 December 2014Secretary of State refused

Project details

Technology
wind farm
Capacity
15 MW
Status (REPD)
refused
Record last updated
1 August 2016
Operator or applicant
Broadview Energy
Planning authority
West Northamptonshire
Planning application reference
S/2010/1437/MAF
Appeal reference
APP/Z2830/A/11/2165035/NWF
Turbines
5
Address (REPD)
land to the north of Welsh Lane between Greatworth and Helmdon
Council area (by location)
West Northamptonshire
Time to decision
36 weeks
REPD reference
4639

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Welsh Lanesolar farm30approved, not built0.8
Halse Road Solar Farm & Battery Storagesolar farm49.9approved, not built3.5
Hall Farmsolar farm5.1operational4.0
Farthinghoe Solar Farmsolar farm10refused4.5
Manor Farm, Whitfieldsolar farm30application submitted5.5
Turweston Solar Farmsolar farm16.7operational7.4
Primrose Hill Farm, Oxford Road Solar Farmsolar farm24application submitted7.6
Litchlake Farmbattery storage10permission expired9.1

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0882, -1.1642).