Gawcott Fields Farm (9.2 MW solar farm)

Gawcott Fields Farm is a 9.2 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 15 December 2015; the record was last updated on 25 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

9.2 MWsolar farm
operationalstatus in REPD
25 April 2016record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
29 July 2014Application submitted
28 October 2014Planning permission granted
2 November 2015Construction started
15 December 2015Operational

Project details

Technology
solar farm
Capacity
9.2 MW
Status (REPD)
operational
Record last updated
25 April 2016
Operator or applicant
Harper Solar Ltd
Planning authority
Buckinghamshire
Planning application reference
14/02293/APP
Site area
29.0 ha
Address (REPD)
Land At Gawcott Fields Farm Gawcott Road Buckingham Buckinghamshire MK18 1TN
Council area (by location)
Buckinghamshire
Time to decision
13 weeks
REPD reference
2227

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farmsolar farm12approved, not built3.4
Land at Thornborough Groundssolar farm5operational5.7
Wicken Farm, Leckhampstead Solar Farmsolar farm21approved, not built7.5
Fox Covert Solar Farmsolar farm22operational7.7
Shelswell Park Solar Farmsolar farm5operational7.8
Thornton Estatesolar farm50application submitted8.1
Turweston Solar Farmsolar farm16.7operational8.4
East Claydon Substation, East Claydon Roadbattery storage500application submitted8.5
Sparrow Lodge Farmsolar farm20approved, not built8.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.9885, -1.005).