Land at Thornborough Grounds (5 MW solar farm)

Land at Thornborough Grounds is a 5 MW solar farm project in Buckinghamshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2016; the record was last updated on 5 July 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
5 July 2018record last updated
Buckinghamshirecouncil area

Planning timeline

DateStage
11 March 2015Application submitted
10 June 2015Planning permission granted
11 January 2016Construction started
31 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
5 July 2018
Operator or applicant
NESF (formerly Lark Energy)
Planning authority
Buckinghamshire
Planning application reference
15/00723/APP
Site area
12.8 ha
Address (REPD)
Land at Thornborough Grounds, Bletchley Road, Thornborough
Council area (by location)
Buckinghamshire
Time to decision
13 weeks
REPD reference
5092

Who decides

ApplicationsBuckinghamshireUK
Decided applications (solar, wind, battery)8010,236
Refused19 (24%)19%
Solar refused14 of 6812%
Onshore wind refused2 of 345%
Battery storage refused3 of 916%
Median time from submission to decision15.4 weeks17.0 weeks
Appeals lodged / allowed6 / 7—

Other large projects within 10 km

ProjectTypeMWStatuskm
Manor Farmsolar farm12approved, not built2.4
Wicken Farm, Leckhampstead Solar Farmsolar farm21approved, not built2.6
Thornton Estatesolar farm50application submitted2.7
Manor Farm, Beachampton Solar Farmsolar farm25approved, not built3.4
Sparrow Lodge Farmsolar farm20approved, not built3.7
Stratford Road Solar Farmsolar farm5approved, not built4.1
Mount Mill Farmsolar farm12operational4.2
Stony Energy Storage Facilitybattery storage79.9operational4.2
Land At Potash Farmsolar farm7operational4.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0078, -0.9272).