Energy Projects Near You

Mount Mill Farm (12 MW solar farm)

Mount Mill Farm is a 12 MW solar farm project in West Northamptonshire, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2015; the record was last updated on 19 May 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

12 MWsolar farm
operationalstatus in REPD
19 May 2015record last updated
West Northamptonshirecouncil area

Planning timeline

DateStage
8 August 2014Application submitted
25 September 2014Planning permission granted
1 January 2015Construction started
30 March 2015Operational

Project details

Technology
solar farm
Capacity
12 MW
Status (REPD)
operational
Record last updated
19 May 2015
Operator or applicant
OPDE
Planning authority
West Northamptonshire
Planning application reference
S/2014/1374/MAF
Site area
30.1 ha
Address (REPD)
Mount Mill Farm, Stratford Road, Wicken
Council area (by location)
West Northamptonshire
Time to decision
7 weeks
REPD reference
2228

Earlier applications for this site

ApplicationMWSubmittedOutcome
Mount Mill Farm S/2014/0470/MAF184 April 2014refused 11 June 2014

Who decides

ApplicationsWest NorthamptonshireUK
Decided applications (solar, wind, battery)8710,236
Refused23 (26%)19%
Solar refused12 of 6512%
Onshore wind refused9 of 1245%
Battery storage refused2 of 1016%
Median time from submission to decision13.0 weeks17.0 weeks
Appeals lodged / allowed7 / 10—

Other large projects within 10 km

ProjectTypeMWStatuskm
Sparrow Lodge Farmsolar farm20approved, not built0.6
Silver Spinney Farmbattery storage5under construction1.2
Wicken Farm, Leckhampstead Solar Farmsolar farm21approved, not built2.0
Manor Farm, Beachampton Solar Farmsolar farm25approved, not built2.2
Stony Energy Storage Facilitybattery storage79.9operational2.9
Land At Potash Farmsolar farm7operational3.3
Stratford Road Solar Farmsolar farm5approved, not built3.3
Oaks Farm Solar Farmsolar farm37approved, not built3.8
Thornton Estatesolar farm50application submitted4.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (52.0394, -0.8943).