Solar, wind and battery projects near Milton Keynes (MK8)
95 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of MK8 (Milton Keynes): 6 are waiting for a planning decision, 62 approved but not yet running, 11 operational. The largest live scheme is Thornton Estate (50 MW solar farm, application submitted on 23 July 2025, no decision recorded), 6.5 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of MK8
Projects of 1 MW and more (23)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Oaks Farm Solar Farmsolar farm | solar farm | 37 | approved, not builtupdated Jul 2026 | Jul 2025 | granted May 2026 | Jul 2026 | Buckinghamshire | 3.1 |
| Land At Potash Farmsolar farm | solar farm | 7 | operationalupdated Sep 2015 | Feb 2011 | granted Apr 2011 | Sep 2015 | Buckinghamshire | 4.3 |
| Stony Energy Storage Facilitybattery storage | battery storage | 79.9 | operationalupdated May 2024 | Jul 2017 | granted Sep 2021 | May 2024 | Buckinghamshire | 4.5 |
| Stratford Road Solar Farmsolar farm | solar farm | 5 | approved, not built may be out of dateupdated Dec 2021 | Dec 2020 | granted Jan 2022 | Dec 2021 | Buckinghamshire | 4.7 |
| DHL Supply Chain, Pendeen Crescent -Solar Panelsrooftop solar | rooftop solar | 1.2 | approved, not builtupdated Aug 2024 | Jun 2024 | granted Jul 2024 | Aug 2024 | Milton Keynes | 4.8 |
| Pendeen Crescent, Snelshall Eastrooftop solar | rooftop solar | 1.2 | application submitted may be out of dateupdated Apr 2024 | Apr 2024 | — | Apr 2024 | Milton Keynes | 4.9 |
| Delico, Steinbeck Crescentrooftop solar | rooftop solar | 1.6 | approved, not built may be out of dateupdated May 2023 | Jan 2023 | granted Apr 2023 | May 2023 | Milton Keynes | 5.0 |
| Manor Farm, Beachampton Solar Farmsolar farm | solar farm | 25 | approved, not builtupdated Apr 2026 | Oct 2022 | granted Jan 2024 | Apr 2026 | Buckinghamshire | 5.3 |
| Mount Mill Farmsolar farm | solar farm | 12 | operationalupdated May 2015 | Aug 2014 | granted Sep 2014 | May 2015 | West Northamptonshire | 6.0 |
| Knotwood Fields Farmsolar farm | solar farm | 2.6 | permission expiredupdated Aug 2019 | Sep 2015 | granted Dec 2015 | Aug 2019 | West Northamptonshire | 6.0 |
| Orchard Way Wind Farmwind farm | wind farm | 15 | refused on appealupdated Aug 2014 | Sep 2011 | refused Nov 2012 | Aug 2014 | Milton Keynes | 6.2 |
| Mercedes Benz UK Solar array car portrooftop solar | rooftop solar | 2 | approved, not built may be out of dateupdated Dec 2021 | Jun 2021 | granted Sep 2021 | Dec 2021 | Milton Keynes | 6.2 |
| Sparrow Lodge Farmsolar farm | solar farm | 20 | approved, not built may be out of dateupdated May 2023 | Nov 2019 | granted Mar 2021 | May 2023 | West Northamptonshire | 6.5 |
| Thornton Estatesolar farm | solar farm | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Buckinghamshire | 6.5 |
| Silver Spinney Farmbattery storage | battery storage | 5 | under constructionupdated Apr 2021 | Jan 2019 | — | Apr 2021 | West Northamptonshire | 6.8 |
| Wicken Farm, Leckhampstead Solar Farmsolar farm | solar farm | 21 | approved, not builtupdated Jan 2024 | Jan 2022 | granted Dec 2023 | Jan 2024 | West Northamptonshire | 7.7 |
| Salden Wind Farmwind farm | wind farm | 10 | refusedupdated Sep 2015 | Dec 2013 | refused Aug 2015 | Sep 2015 | Buckinghamshire | 7.7 |
| Wood End, Mursley Roadsolar farm | solar farm | 36 | approved, not built may be out of dateupdated May 2022 | Jan 2020 | granted Dec 2022 | May 2022 | Buckinghamshire | 7.7 |
| Yardley Road Solar Farmsolar farm | solar farm | 40 | application submittedupdated Aug 2025 | Jun 2025 | — | Aug 2025 | West Northamptonshire | 7.8 |
| The Kicklessolar farm | solar farm | 5 | operationalupdated Apr 2016 | May 2014 | granted Nov 2014 | Apr 2016 | Milton Keynes | 8.3 |
| Land at Thornborough Groundssolar farm | solar farm | 5 | operationalupdated Jul 2018 | Mar 2015 | granted Jun 2015 | Jul 2018 | Buckinghamshire | 8.6 |
| Chippenham Drive, Kingstonrooftop solar | rooftop solar | 1.8 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Milton Keynes | 8.7 |
| Prospect Farmsolar farm | solar farm | 1.2 | permission expiredupdated Aug 2018 | Mar 2015 | granted Jun 2015 | Aug 2018 | Buckinghamshire | 9.2 |
Smaller schemes under 1 MW, mostly rooftop solar (60)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Stone Hill Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Jan 2025 | Nov 2024 | — | Jan 2025 | Milton Keynes | 0.4 |
| The Church Of The Latterday Saints, The High Streetbattery storage | battery storage | 0.2 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | Milton Keynes | 1.0 |
| Volkswagen Group UK, Garamonde Driverooftop solar | rooftop solar | 0.7 | approved, not builtupdated Dec 2025 | Sep 2024 | granted Jan 2025 | Dec 2025 | Milton Keynes | 1.3 |
| Paynes Drive & Linceslade Grove, Loughton - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | refusedupdated Apr 2025 | Nov 2024 | refused Feb 2025 | Apr 2025 | Milton Keynes | 1.3 |
| Brioche Pasquier UK, Garamonde Drive Solar Canopiesrooftop solar | rooftop solar | 0.6 | approved, not builtupdated Feb 2025 | Oct 2024 | granted Jan 2025 | Feb 2025 | Milton Keynes | 1.4 |
| Brioche Pasquier, Garamonde Driverooftop solar | rooftop solar | 0.9 | refusedupdated May 2024 | Mar 2024 | refused May 2024 | May 2024 | Milton Keynes | 1.5 |
| Ingram Content Group UK, Chapter Houserooftop solar | rooftop solar | 1 | approved, not builtupdated Aug 2023 | Jun 2023 | granted Aug 2023 | Aug 2023 | Milton Keynes | 1.5 |
| Bradwell Road - Micro Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Jan 2026 | Jan 2026 | Milton Keynes | 1.5 |
| The Hazeley Academyrooftop solar | rooftop solar | 0.2 | operationalupdated Oct 2019 | Feb 2019 | granted May 2020 | Oct 2019 | Milton Keynes | 1.6 |
| Bradwell Road, Loughton Lodgerooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2022 | Apr 2022 | granted Jun 2022 | Jun 2022 | Milton Keynes | 1.6 |
| Alston Drive, Bradwell Abbey - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 | Milton Keynes | 1.7 |
| Deltic Avenue, Rooksleyrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Milton Keynes | 2.0 |
| Hodge Lea Lane, Hodge Leabattery storage | battery storage | 0.2 | refusedupdated Feb 2025 | Nov 2024 | refused Jan 2025 | Feb 2025 | Milton Keynes | 2.0 |
| Burners Lane, Kiln Farmrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Aug 2025 | Nov 2025 | Milton Keynes | 2.0 |
| Paxton Crescent, Ackroyd Place - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | application withdrawnupdated Jan 2025 | Nov 2024 | — | Jan 2025 | Milton Keynes | 2.5 |
| Kelvin Drive - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Feb 2025 | Nov 2024 | granted Jan 2025 | Feb 2025 | Milton Keynes | 2.9 |
| Wolverton Swimming And Fitness Centre, Addington Avenuerooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Oct 2025 | Dec 2025 | Milton Keynes | 3.0 |
| Wolverton Swimming & Fitness Centre, Addington Avenuebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Milton Keynes | 3.1 |
| Vodafone, Fingle Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2023 | Jan 2023 | granted Mar 2023 | Apr 2023 | Milton Keynes | 3.1 |
| Fingle Drive, Grafton Streetbattery storage | battery storage | 0.2 | refusedupdated Apr 2025 | Nov 2024 | refused Mar 2025 | Apr 2025 | Milton Keynes | 3.3 |
| Duckworth Court, Oldbrook Boulevard - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Dec 2024 | granted Mar 2025 | Apr 2025 | Milton Keynes | 3.3 |
| The Town Hallrooftop solar | rooftop solar | — | refusedupdated Apr 2021 | Jan 2021 | refused May 2021 | Apr 2021 | Milton Keynes | 3.3 |
| Winterhill Houserooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2021 | Sep 2021 | granted Nov 2021 | Nov 2021 | Milton Keynes | 3.4 |
| Falcon Projectbattery storage | battery storage | 0.3 | operationalupdated Oct 2018 | — | — | Oct 2018 | Milton Keynes | 3.4 |
| New Bradwell School, Bounty Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jun 2026 | Mar 2026 | granted May 2026 | Jun 2026 | Milton Keynes | 3.6 |
| Pear Tree Lane, Bleak Hall - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Nov 2024 | granted Feb 2025 | Apr 2025 | Milton Keynes | 3.8 |
| Verge In Woughton Leisure Centre - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2026 | Oct 2025 | granted Dec 2025 | Jan 2026 | Milton Keynes | 4.0 |
| Snelshall Street, Tattenhoebattery storage | battery storage | 0.2 | application withdrawnupdated Nov 2025 | Jul 2025 | — | Nov 2025 | Milton Keynes | 4.2 |
| The Milton Keynes Academy, Fulwoods Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 | Milton Keynes | 4.2 |
| Linford Wood Business Park, Linford Woodrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | Milton Keynes | 4.3 |
| Grafton Street, End Of Dunsby Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Feb 2025 | Dec 2024 | granted Jan 2025 | Feb 2025 | Milton Keynes | 4.8 |
| St Leger Drive, Great Linford - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Nov 2024 | granted Feb 2025 | Apr 2025 | Milton Keynes | 5.2 |
| Thornbury, West Ashlandrooftop solar | rooftop solar | 0.9 | approved, not builtupdated Apr 2023 | Jan 2023 | granted Mar 2023 | Apr 2023 | Milton Keynes | 5.5 |
| Whaddon Way, Shenley Road - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | refusedupdated Dec 2025 | Oct 2025 | refused Dec 2025 | Dec 2025 | Milton Keynes | 5.6 |
| David Lloyd, Livingstone Driverooftop solar | rooftop solar | 0.6 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Milton Keynes | 5.6 |
| Brickhill Street, Lakeside Roundabout - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 | Milton Keynes | 5.6 |
| Watling Street - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | Jul 2025 | granted Aug 2025 | Nov 2025 | Milton Keynes | 5.7 |
| Langland Road, Netherfield - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | refusedupdated Feb 2026 | Nov 2025 | refused Jan 2026 | Feb 2026 | Milton Keynes | 5.8 |
| Third Avenue, Bletchleyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2025 | Aug 2025 | granted Nov 2025 | Dec 2025 | Milton Keynes | 5.9 |
| Saxon Street, Dawson Roadbattery storage | battery storage | 0.2 | application withdrawnupdated Jul 2025 | Jun 2025 | — | Jul 2025 | Milton Keynes | 5.9 |
| Dawson Road, Bletchleyrooftop solar | rooftop solar | 0.3 | application submitted may be out of dateupdated Oct 2021 | Oct 2021 | — | Oct 2021 | Milton Keynes | 6.0 |
| Dawson Road, Bletchleyrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2022 | Jun 2022 | granted Aug 2022 | Jun 2022 | Milton Keynes | 6.2 |
| Dawson Rentals Vans, Dawson Road Solar Carport Canopy & BESSrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jun 2024 | Apr 2024 | granted May 2024 | Jun 2024 | Milton Keynes | 6.2 |
| Unit 2, Watling Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | May 2024 | granted Jul 2024 | Jul 2024 | Milton Keynes | 6.4 |
| Yeomans Drive, Blakelands - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Jan 2025 | granted Mar 2025 | May 2025 | Milton Keynes | 6.5 |
| Dukes Drive, Princes Way - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated May 2025 | Jan 2025 | granted Mar 2025 | May 2025 | Milton Keynes | 6.6 |
| Tanners Drive, Blakelandsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2023 | Jul 2023 | granted Sep 2023 | Sep 2023 | Milton Keynes | 6.6 |
| Delaware Drive, Tongwellrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Nov 2024 | Jan 2025 | Milton Keynes | 6.7 |
| Wolverton Road, Giffard Park Roundabout - Micro Energy Storagebattery storage | battery storage | 0.2 | application submittedupdated Feb 2025 | Feb 2025 | — | Feb 2025 | Milton Keynes | 6.7 |
| Sensient Flavours, Bilton Roadrooftop solar | rooftop solar | 0.5 | approved, not builtupdated Jun 2023 | Apr 2023 | granted May 2023 | Jun 2023 | Milton Keynes | 6.9 |
| Northfield Drive, Tongwell Street - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Apr 2025 | Dec 2024 | granted Feb 2025 | Apr 2025 | Milton Keynes | 7.0 |
| Northfield Drive, Northfield Solar Panlesrooftop solar | rooftop solar | 0.8 | approved, not builtupdated Feb 2022 | Feb 2022 | granted Mar 2022 | Feb 2022 | Milton Keynes | 7.1 |
| Hammerwood Gate, By University Roundabout - Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Mar 2026 | Dec 2025 | granted Jan 2026 | Mar 2026 | Milton Keynes | 7.2 |
| Northfield Drive, Northfield Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Apr 2024 | Feb 2024 | granted Mar 2024 | Apr 2024 | Milton Keynes | 7.3 |
| The Premier Academy, Saffron Streetrooftop solar | rooftop solar | — | approved, not builtupdated Jan 2026 | Nov 2025 | granted Dec 2025 | Jan 2026 | Milton Keynes | 7.5 |
| Caldecote Farm - Storage & Distribution Unitrooftop solar | rooftop solar | 0.3 | under constructionupdated Jan 2025 | Sep 2021 | granted Jul 2023 | Jan 2025 | Milton Keynes | 7.6 |
| Belvedere Lane, Watling Street - Micro Energy Storagebattery storage | battery storage | 0.2 | application submitted | Apr 2026 | — | — | Milton Keynes | 7.8 |
| Standing Way -Micro Energy Storagebattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2025 | May 2025 | granted Jul 2025 | Nov 2025 | Milton Keynes | 8.0 |
| The Venue MK, Hindhead Knoll - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Dec 2025 | Oct 2025 | granted Dec 2025 | Dec 2025 | Milton Keynes | 8.0 |
| Sir Herbert Leon Academyrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Sep 2021 | Feb 2021 | granted Apr 2021 | Sep 2021 | Milton Keynes | 8.1 |
12 more projects not listed (furthest or smallest).
Distance from the average position of the MK8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 14 | 2 | 6 | 4 | 0 | 234 |
| Rooftop solar | 43 | 2 | 35 | 4 | 2 | 20.8 |
| Wind farm | 2 | 0 | 0 | 0 | 2 | 0 |
| Battery storage | 36 | 2 | 21 | 3 | 5 | 9.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Milton Keynes decides solar, wind and battery applications
| Applications | Milton Keynes | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 77 | 10,236 |
| Refused | 10 (13%) | 19% |
| Solar refused | 4 of 49 | 12% |
| Onshore wind refused | 1 of 2 | 45% |
| Battery storage refused | 5 of 26 | 16% |
| Median time from submission to decision | 7.9 weeks | 17.0 weeks |
| Appeals lodged / allowed | 0 / 0 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near MK8, 7 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.